A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
30
27
25
24
The correct Answer is:B
To solve the problem step by step, we will first determine the work rates of A, B, and C, and then calculate how long it would take C to finish the entire work alone.
Step 1: Determine the work rates of A and B
- A can complete the work in 30 days. Therefore, A's work rate is:
Work rate of A=130 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)
Step 2: Calculate the combined work rate of A and B
When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=130+120
To add these fractions, we need a common denominator. The least common multiple of 30 and 20 is 60.
130=260,120=360
Thus,
Combined work rate=260+360=560=112 (work per day)
Step 3: Calculate the work done by A and B in 4 days
In 4 days, the amount of work done by A and B together is:
Work done in 4 days=Combined work rate×4=112×4=412=13
Step 4: Determine the remaining work
Since A and B completed 13 of the work, the remaining work is:
Remaining work=1−13=23
Step 5: Calculate the time taken by C to finish the remaining work
It is given that C finishes the remaining 23 of the work in 18 days. Therefore, we can find C's work rate:
Work rate of C=Remaining workTime taken=2318=23×18=254=127 (work per day)
Step 6: Calculate the total time taken by C to finish the whole work
If C can do 127 of the work in a day, then the total time C would take to finish the entire work is:
Total time for C=1Work rate of C=1127=27 days
Final Answer
C alone will finish the whole work in 27 days.
---
- A can complete the work in 30 days. Therefore, A's work rate is:
Work rate of A=130 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)
When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=130+120
To add these fractions, we need a common denominator. The least common multiple of 30 and 20 is 60.
130=260,120=360
Thus,
Combined work rate=260+360=560=112 (work per day)
In 4 days, the amount of work done by A and B together is:
Work done in 4 days=Combined work rate×4=112×4=412=13
Since A and B completed 13 of the work, the remaining work is:
Remaining work=1−13=23
It is given that C finishes the remaining 23 of the work in 18 days. Therefore, we can find C's work rate:
Work rate of C=Remaining workTime taken=2318=23×18=254=127 (work per day)
If C can do 127 of the work in a day, then the total time C would take to finish the entire work is:
Total time for C=1Work rate of C=1127=27 days
C alone will finish the whole work in 27 days.
Similar Questions
A can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionA, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?
View Solution
Knowledge Check
A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
A24B18C36D42P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
A10B16C15D20A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?
A25 daysB30 daysC24 daysD20 days
Deepak can do a piece of work in 25 days and Ashok can do the same work in 40 days. They work together for 5 days and then Deepak goes away. In how many days will Ashok finish the remaining work?
View SolutionA can do a piece of work in 10 days and B can dothe same piece of work in 20 days. They start the work together but after 5 days A leaves off. B will do the remaining piece of work in..
View SolutionVaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?
View SolutionA and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
View SolutionA and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
View Solution