A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?

A

30

B

27

C

25

D

24

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work rates of A, B, and C, and then calculate how long it would take C to finish the entire work alone.

Step 1: Determine the work rates of A and B
- A can complete the work in 30 days. Therefore, A's work rate is:
Work rate of A=130 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)

Step 2: Calculate the combined work rate of A and B
When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=130+120
To add these fractions, we need a common denominator. The least common multiple of 30 and 20 is 60.
130=260,120=360
Thus,
Combined work rate=260+360=560=112 (work per day)

Step 3: Calculate the work done by A and B in 4 days
In 4 days, the amount of work done by A and B together is:
Work done in 4 days=Combined work rate×4=112×4=412=13

Step 4: Determine the remaining work
Since A and B completed 13 of the work, the remaining work is:
Remaining work=113=23

Step 5: Calculate the time taken by C to finish the remaining work
It is given that C finishes the remaining 23 of the work in 18 days. Therefore, we can find C's work rate:
Work rate of C=Remaining workTime taken=2318=23×18=254=127 (work per day)

Step 6: Calculate the total time taken by C to finish the whole work
If C can do 127 of the work in a day, then the total time C would take to finish the entire work is:
Total time for C=1Work rate of C=1127=27 days

Final Answer
C alone will finish the whole work in 27 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

    A24
    B18
    C36
    D42
  • P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

    A10
    B16
    C15
    D20
  • A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then both leave the work. Then Calone finIshes the remaining work in 10 days. In how many days will finish the full work?

    A25 days
    B30 days
    C24 days
    D20 days