If 24 men can do a work in 15 days by working 12 hours daily, then in how many days will 36 men be able to do double the quantum of work, by working 10 hours daily?
30
32
24
12
The correct Answer is:C
To solve the problem, we need to follow these steps:
Step 1: Calculate the total work done by 24 men in 15 days.
The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
Given:
- Number of Men = 24
- Number of Days = 15
- Hours per Day = 12
So, the total work is:
Total Work=24×15×12
Calculating this:
Total Work=24×15=360
Total Work=360×12=4320 man-hours
Step 2: Determine the total work needed for double the quantum of work.
Since we need double the work:
Double Work=2×4320=8640 man-hours
Step 3: Calculate the daily work done by 36 men working 10 hours daily.
Now, we need to find out how many days it will take for 36 men to do 8640 man-hours of work, working 10 hours a day.
First, calculate the daily work done by 36 men:
Daily Work=Number of Men×Hours per Day
Daily Work=36×10=360 man-hours per day
Step 4: Calculate the number of days required to complete the double work.
Now, we can find the number of days required to complete the double work:
Number of Days=Total WorkDaily Work
Number of Days=8640360
Calculating this:
Number of Days=24
Final Answer:
The number of days required for 36 men to complete double the work by working 10 hours daily is 24 days.
---
The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- Number of Men = 24
- Number of Days = 15
- Hours per Day = 12
Total Work=24×15×12
Total Work=24×15=360
Total Work=360×12=4320 man-hours
Since we need double the work:
Double Work=2×4320=8640 man-hours
Now, we need to find out how many days it will take for 36 men to do 8640 man-hours of work, working 10 hours a day.
Daily Work=Number of Men×Hours per Day
Daily Work=36×10=360 man-hours per day
Now, we can find the number of days required to complete the double work:
Number of Days=Total WorkDaily Work
Number of Days=8640360
Number of Days=24
The number of days required for 36 men to complete double the work by working 10 hours daily is 24 days.
Similar Questions
A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution
Knowledge Check
- Question 1 - Select One
If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
Aa) 15Bb) 12Cc) 10Dd) 16 - Question 2 - Select One
If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
A30B25C48D35 - Question 3 - Select One
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
AA. 16BB. 15CC. 10DD. 12
A can do a work in 36 days and B in 12 days. If they work to gether in how many days will they be able to do the work?
View Solution38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?
View Solution45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
View Solution15 men can do a work in 20 days. How many days will 10 men take to do double the same work0
View SolutionIf 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?
View Solution