If 24 men can do a work in 15 days by working 12 hours daily, then in how many days will 36 men be able to do double the quantum of work, by working 10 hours daily?

A

30

B

32

C

24

D

12

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to follow these steps:

Step 1: Calculate the total work done by 24 men in 15 days.
The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day

Given:
- Number of Men = 24
- Number of Days = 15
- Hours per Day = 12

So, the total work is:
Total Work=24×15×12

Calculating this:
Total Work=24×15=360
Total Work=360×12=4320 man-hours

Step 2: Determine the total work needed for double the quantum of work.
Since we need double the work:
Double Work=2×4320=8640 man-hours

Step 3: Calculate the daily work done by 36 men working 10 hours daily.
Now, we need to find out how many days it will take for 36 men to do 8640 man-hours of work, working 10 hours a day.

First, calculate the daily work done by 36 men:
Daily Work=Number of Men×Hours per Day
Daily Work=36×10=360 man-hours per day

Step 4: Calculate the number of days required to complete the double work.
Now, we can find the number of days required to complete the double work:
Number of Days=Total WorkDaily Work
Number of Days=8640360

Calculating this:
Number of Days=24

Final Answer:
The number of days required for 36 men to complete double the work by working 10 hours daily is 24 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?

    Aa) 15
    Bb) 12
    Cc) 10
    Dd) 16
  • Question 2 - Select One

    If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?

    A30
    B25
    C48
    D35
  • Question 3 - Select One

    If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?

    AA. 16
    BB. 15
    CC. 10
    DD. 12