45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
10
16
18
15
The correct Answer is:D
To solve the problem, we will use the concept of man-days, which states that the total amount of work done is equal to the number of men multiplied by the number of days they work.
1. Identify the given information:
- Number of men (m1) = 45
- Number of days (d1) = 12
- Number of men (m2) = 36
- Number of days (d2) = ?
2. Calculate the total work in man-days:
- Total work = Number of men × Number of days
- Total work = m1 × d1 = 45 men × 12 days = 540 man-days
3. Set up the equation for the second scenario:
- Total work = m2 × d2
- Therefore, 540 man-days = 36 men × d2
4. Solve for d2:
- Rearranging the equation gives us:
d2=540 man-days36 men
- Now, perform the division:
d2=15 days
5. Conclusion:
- Therefore, 36 men will be able to complete the work in 15 days.
Final Answer:
The answer is 15 days (Option D).
---
- Number of men (m1) = 45
- Number of days (d1) = 12
- Number of men (m2) = 36
- Number of days (d2) = ?
- Total work = Number of men × Number of days
- Total work = m1 × d1 = 45 men × 12 days = 540 man-days
- Total work = m2 × d2
- Therefore, 540 man-days = 36 men × d2
- Rearranging the equation gives us:
d2=540 man-days36 men
- Now, perform the division:
d2=15 days
- Therefore, 36 men will be able to complete the work in 15 days.
The answer is 15 days (Option D).
Similar Questions
Knowledge Check
12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
A60 daysB45 daysC54 daysD48 daysIf 45 men can do a piece of work in 49 days, in how many days will 35 men do it?
A63B53C43D337 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
A28B21C14D7
If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View Solution7 men can complete a work in 52 days. In how many days will 13 men finish the same work.
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution34 men can do a piece of work in 12 days . How many days will 51 men take to do it
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View Solution