If 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?

A

3

B

2

C

4

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to determine how many days it will take for 10 men to reap the same field while working 8 hours a day, given that 4 men can complete the task in 5 days working 12 hours a day.

1. Calculate the Total Work Done by 4 Men:
- The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- Here, we have 4 men, working for 5 days, and 12 hours each day:
Total Work=4 men×5 days×12 hours/day=240 man-hours

2. Set Up the Equation for 10 Men Working 8 Hours a Day:
- Let D be the number of days required for 10 men to complete the same work. The total work done by 10 men working for D days at 8 hours a day is:
Total Work=10 men×D days×8 hours/day
- This can be simplified to:
Total Work=80D man-hours

3. Equate the Two Expressions for Total Work:
- Since both expressions represent the same total work, we can set them equal to each other:
240=80D

4. Solve for D:
- To find D, divide both sides of the equation by 80:
D=24080=3

5. Conclusion:
- Therefore, it will take 10 men working 8 hours a day a total of 3 days to reap the same field.

Final Answer:
3 days

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?

    AA. 16
    BB. 15
    CC. 10
    DD. 12
  • Question 2 - Select One

    If 5 men working 6 hours a day can reap a field in 20 days. In how many days will 15 men reap the field, working 8 hours a day ?

    A5 days
    B6 days
    C7 1/2 days
    D9 days
  • Question 3 - Select One

    If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?

    A30
    B25
    C48
    D35