If 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?
3
2
4
6
The correct Answer is:A
To solve the problem, we need to determine how many days it will take for 10 men to reap the same field while working 8 hours a day, given that 4 men can complete the task in 5 days working 12 hours a day.
1. Calculate the Total Work Done by 4 Men:
- The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- Here, we have 4 men, working for 5 days, and 12 hours each day:
Total Work=4 men×5 days×12 hours/day=240 man-hours
2. Set Up the Equation for 10 Men Working 8 Hours a Day:
- Let D be the number of days required for 10 men to complete the same work. The total work done by 10 men working for D days at 8 hours a day is:
Total Work=10 men×D days×8 hours/day
- This can be simplified to:
Total Work=80D man-hours
3. Equate the Two Expressions for Total Work:
- Since both expressions represent the same total work, we can set them equal to each other:
240=80D
4. Solve for D:
- To find D, divide both sides of the equation by 80:
D=24080=3
5. Conclusion:
- Therefore, it will take 10 men working 8 hours a day a total of 3 days to reap the same field.
Final Answer:
3 days
- The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days×Hours per Day
- Here, we have 4 men, working for 5 days, and 12 hours each day:
Total Work=4 men×5 days×12 hours/day=240 man-hours
- Let D be the number of days required for 10 men to complete the same work. The total work done by 10 men working for D days at 8 hours a day is:
Total Work=10 men×D days×8 hours/day
- This can be simplified to:
Total Work=80D man-hours
- Since both expressions represent the same total work, we can set them equal to each other:
240=80D
- To find D, divide both sides of the equation by 80:
D=24080=3
- Therefore, it will take 10 men working 8 hours a day a total of 3 days to reap the same field.
3 days
Topper's Solved these Questions
- BOOK - SSC SELECTION POSTCHAPTER - SSC PREVIOUS YEAR PAPER GRADUATION LEVEL ( 18 JAN 2019 SHIFT 3)EXERCISE - GRADUATION LEVEL24videos
SSC PREVIOUS YEAR PAPER GRADUATION LEVEL ( 18 JAN 2019 SHIFT 3)
- BOOK - SSC SELECTION POSTCHAPTER - SSC PREVIOUS YEAR PAPER GRADUATION LEVEL (17 JAN 2019 SHIFT 3)EXERCISE - Section: Graduation Level19videos
SSC PREVIOUS YEAR PAPER GRADUATION LEVEL (17 JAN 2019 SHIFT 3)
Similar Questions
Knowledge Check
- Question 1 - Select One
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
AA. 16BB. 15CC. 10DD. 12 - Question 2 - Select One
If 5 men working 6 hours a day can reap a field in 20 days. In how many days will 15 men reap the field, working 8 hours a day ?
A5 daysB6 daysC7 1/2 daysD9 days - Question 3 - Select One
If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
A30B25C48D35
12 men can reap a field in 25 days. In how many days can 20 mean reap the same field?
View SolutionIf 30 men can reap a field in 17 days, then 10 men reap the field in how many days?
View SolutionIf 30men working 18h per day can reap a field in 32 days, in how many days can 36 men reap the field working 16h per day ?
View Solution12 men can reap a field in 25 days. In how many days can 20 men reap the same field?
View SolutionIf 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day ?
View Solution