A certain number of persons can complete a piece of work in 46 days. If there were 8 persons more, the work could be finished in 16 days less. How many persons were originally there ?
25
18
15
20
The correct Answer is:C
To solve the problem step by step, we can follow these steps:
Step 1: Define the Variables
Let the original number of persons be x.
Step 2: Establish the Work Equation
The total work can be expressed in terms of the number of persons and the number of days they take to complete the work. If x persons can complete the work in 46 days, the total work W can be given by:
W=x×46
Step 3: Set Up the New Work Equation
If there are 8 more persons, the total number of persons becomes x+8. According to the problem, with these additional persons, the work can be finished in 30 days (16 days less than 46 days). Thus, the work can also be expressed as:
W=(x+8)×30
Step 4: Set the Two Expressions for Work Equal
Since both expressions represent the same total work W, we can set them equal to each other:
x×46=(x+8)×30
Step 5: Expand and Simplify the Equation
Expanding the right side:
46x=30x+240
Now, subtract 30x from both sides:
46x−30x=240
This simplifies to:
16x=240
Step 6: Solve for x
Now, divide both sides by 16:
x=24016=15
Conclusion
The original number of persons is 15.
---
Let the original number of persons be x.
The total work can be expressed in terms of the number of persons and the number of days they take to complete the work. If x persons can complete the work in 46 days, the total work W can be given by:
W=x×46
If there are 8 more persons, the total number of persons becomes x+8. According to the problem, with these additional persons, the work can be finished in 30 days (16 days less than 46 days). Thus, the work can also be expressed as:
W=(x+8)×30
Since both expressions represent the same total work W, we can set them equal to each other:
x×46=(x+8)×30
Expanding the right side:
46x=30x+240
Now, subtract 30x from both sides:
46x−30x=240
This simplifies to:
16x=240
Now, divide both sides by 16:
x=24016=15
The original number of persons is 15.
Similar Questions
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution
Knowledge Check
A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?
A17B24C30D22a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
A17B24C30D22A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
A1. 17B2. 24C3. 30D4. 22
A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially ?
View Solution'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View Solution