A and B can complete a work in 12 days and 20 days, respectively They work together for 4 days. C alone completes the remaining work in 14 days. B and C together can complete the same work in:
16 days
12 days
15 days
10 days
The correct Answer is:B
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A and B
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)
Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B when they work together is:
Combined work rate of A and B=112+120
- To add these fractions, we find a common denominator, which is 60:
112=560,120=360
- Therefore,
Combined work rate of A and B=560+360=860=215 (work per day)
Step 3: Calculate the work done by A and B in 4 days
- In 4 days, the amount of work done by A and B together is:
Work done in 4 days=4×215=815
Step 4: Determine the remaining work
- The total work can be considered as 1 (or 60 units for easier calculation). The remaining work after A and B have worked for 4 days is:
Remaining work=1−815=1515−815=715
Step 5: Calculate C's work rate
- C completes the remaining work in 14 days. Therefore, C's work rate is:
Work rate of C=71514=715×14=7210=130 (work per day)
Step 6: Calculate the combined work rate of B and C
- Now we find the combined work rate of B and C:
Combined work rate of B and C=Work rate of B+Work rate of C=120+130
- To add these fractions, we find a common denominator, which is 60:
120=360,130=260
- Therefore,
Combined work rate of B and C=360+260=560=112 (work per day)
Step 7: Calculate the time taken by B and C to complete the work
- The time taken by B and C to complete the entire work (1 unit) is:
Time=1Combined work rate of B and C=1112=12 days
Final Answer
B and C together can complete the work in 12 days.
---
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)
- The combined work rate of A and B when they work together is:
Combined work rate of A and B=112+120
- To add these fractions, we find a common denominator, which is 60:
112=560,120=360
- Therefore,
Combined work rate of A and B=560+360=860=215 (work per day)
- In 4 days, the amount of work done by A and B together is:
Work done in 4 days=4×215=815
- The total work can be considered as 1 (or 60 units for easier calculation). The remaining work after A and B have worked for 4 days is:
Remaining work=1−815=1515−815=715
- C completes the remaining work in 14 days. Therefore, C's work rate is:
Work rate of C=71514=715×14=7210=130 (work per day)
- Now we find the combined work rate of B and C:
Combined work rate of B and C=Work rate of B+Work rate of C=120+130
- To add these fractions, we find a common denominator, which is 60:
120=360,130=260
- Therefore,
Combined work rate of B and C=360+260=560=112 (work per day)
- The time taken by B and C to complete the entire work (1 unit) is:
Time=1Combined work rate of B and C=1112=12 days
B and C together can complete the work in 12 days.
Similar Questions
A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View Solution
Knowledge Check
A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
A8 daysB5 daysC4 daysD6 daysA can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 daysA can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
A212 daysB3 daysC112 daysD2 days
A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionA, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए वे इस कार्य को कितने दिनों में समाप्त करेंगे ?
View SolutionA, B and C can complete a piece of work in 5, 20 and 60 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 5, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इस कार्य को कितने दिनों में पूरा करेंगे ?
View Solution