A and B can complete a work in 12 days and 20 days, respectively They work together for 4 days. C alone completes the remaining work in 14 days. B and C together can complete the same work in:

A

16 days

B

12 days

C

15 days

D

10 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work rates of A and B
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)

Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B when they work together is:
Combined work rate of A and B=112+120
- To add these fractions, we find a common denominator, which is 60:
112=560,120=360
- Therefore,
Combined work rate of A and B=560+360=860=215 (work per day)

Step 3: Calculate the work done by A and B in 4 days
- In 4 days, the amount of work done by A and B together is:
Work done in 4 days=4×215=815

Step 4: Determine the remaining work
- The total work can be considered as 1 (or 60 units for easier calculation). The remaining work after A and B have worked for 4 days is:
Remaining work=1815=1515815=715

Step 5: Calculate C's work rate
- C completes the remaining work in 14 days. Therefore, C's work rate is:
Work rate of C=71514=715×14=7210=130 (work per day)

Step 6: Calculate the combined work rate of B and C
- Now we find the combined work rate of B and C:
Combined work rate of B and C=Work rate of B+Work rate of C=120+130
- To add these fractions, we find a common denominator, which is 60:
120=360,130=260
- Therefore,
Combined work rate of B and C=360+260=560=112 (work per day)

Step 7: Calculate the time taken by B and C to complete the work
- The time taken by B and C to complete the entire work (1 unit) is:
Time=1Combined work rate of B and C=1112=12 days

Final Answer
B and C together can complete the work in 12 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days
  • A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :

    A212 days
    B3 days
    C112 days
    D2 days