Twenty persons take 15 days to complete a certain work, working 8 hours a day. To complete the same work in 4 days. working 10 hours a day. the number of persons required is:
75
60
80
55
The correct Answer is:B
To solve the problem, we need to use the concept of work, which can be expressed in terms of the number of persons (M), the number of days (D), and the number of hours worked per day (H). The formula we will use is:
M1×D1×H1=M2×D2×H2
Where:
- M1 = Initial number of persons
- D1 = Initial number of days
- H1 = Initial hours per day
- M2 = Required number of persons
- D2 = Required number of days
- H2 = Required hours per day
1. Identify the given values:
- M1=20 persons
- D1=15 days
- H1=8 hours/day
- D2=4 days
- H2=10 hours/day
2. Substitute the values into the formula:
20×15×8=M2×4×10
3. Calculate the left side of the equation:
20×15=300
300×8=2400
So, the left side equals 2400.
4. Set up the equation:
2400=M2×4×10
5. Calculate the right side:
4×10=40
So, we have:
2400=M2×40
6. Solve for M2:
M2=240040
M2=60
Thus, the number of persons required to complete the work in 4 days, working 10 hours a day, is 60 persons.
- M1 = Initial number of persons
- D1 = Initial number of days
- H1 = Initial hours per day
- M2 = Required number of persons
- D2 = Required number of days
- H2 = Required hours per day
- M1=20 persons
- D1=15 days
- H1=8 hours/day
- D2=4 days
- H2=10 hours/day
20×15×8=M2×4×10
20×15=300
300×8=2400
So, the left side equals 2400.
2400=M2×4×10
4×10=40
So, we have:
2400=M2×40
M2=240040
M2=60
Similar Questions
12 men working 8 hours per day complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required is a. 4 b. 5 c. 6 d. 8
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View Solution
Knowledge Check
If 30 persons take 10 days to complete a certain work working 8 hours a day. Then 40 persons should work how many hours a day so that the work is completed in 6 days?
यदि 30 लोग प्रतिदिन 8 घंटे कार्य करके किसी कार्य को 10 दिनों में पूरा करते हैं, तो इस कार्य को 6 दिनों में पूरा करने के लिए 40 व्यक्ति दिन में कितने घंटे कार्य करेंगे ?A6B10C8D12Working 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
A3 daysB4 daysC4.5 daysD5.4 daysWorking 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
A3 daysB4 daysC4.5 daysD5.4 days
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5511 b. 5611 c. 6611 d. 6611
View SolutionP can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?
View SolutionFifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
View SolutionA can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
View Solution