Twenty persons take 15 days to complete a certain work, working 8 hours a day. To complete the same work in 4 days. working 10 hours a day. the number of persons required is:

A

75

B

60

C

80

D

55

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to use the concept of work, which can be expressed in terms of the number of persons (M), the number of days (D), and the number of hours worked per day (H). The formula we will use is:

M1×D1×H1=M2×D2×H2

Where:
- M1 = Initial number of persons
- D1 = Initial number of days
- H1 = Initial hours per day
- M2 = Required number of persons
- D2 = Required number of days
- H2 = Required hours per day

1. Identify the given values:
- M1=20 persons
- D1=15 days
- H1=8 hours/day
- D2=4 days
- H2=10 hours/day

2. Substitute the values into the formula:
20×15×8=M2×4×10

3. Calculate the left side of the equation:
20×15=300
300×8=2400
So, the left side equals 2400.

4. Set up the equation:
2400=M2×4×10

5. Calculate the right side:
4×10=40
So, we have:
2400=M2×40

6. Solve for M2:
M2=240040
M2=60

Thus, the number of persons required to complete the work in 4 days, working 10 hours a day, is 60 persons.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • If 30 persons take 10 days to complete a certain work working 8 hours a day. Then 40 persons should work how many hours a day so that the work is completed in 6 days?
    यदि 30 लोग प्रतिदिन 8 घंटे कार्य करके किसी कार्य को 10 दिनों में पूरा करते हैं, तो इस कार्य को 6 दिनों में पूरा करने के लिए 40 व्यक्ति दिन में कितने घंटे कार्य करेंगे ?

    A6
    B10
    C8
    D12
  • Working 5 hours a day. A can complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

    A3 days
    B4 days
    C4.5 days
    D5.4 days
  • Working 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

    A3 days
    B4 days
    C4.5 days
    D5.4 days