If a man completes 37 work in 6 days , then how many more days will be require for completing the remaining work ?

A

8

B

14

C

9

D

7

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these instructions:

Step 1: Understand the total work done
The man completes 37 of the work in 6 days.

Step 2: Determine the total work
Let the total work be represented as 7x. This means that 37 of the total work is 3x.

Step 3: Calculate the remaining work
The remaining work can be calculated as:
Remaining work=Total workWork done=7x3x=4x

Step 4: Find the rate of work
Since the man completes 3x in 6 days, we can find the rate of work per day:
Rate of work=3x6=x2 (work per day)

Step 5: Calculate the time required to complete the remaining work
To find out how many days it will take to complete the remaining work 4x:
Days required=Remaining workRate of work=4xx2=4x×2x=8 days

Conclusion
Thus, the man will require 8 more days to complete the remaining work.

---

|


Similar Questions


Knowledge Check

  • 20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

    A8
    B10
    C15
    D20
  • 20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

    AA) 8
    BB) 10
    CC) 15
    DD) 20
  • A work can be completed by 18 boys in 24 days. If 6 boys leave after working for 12 days, how many days will be needed to complete the remaining work?

    A12
    B15
    C18
    D24