If a man completes 37 work in 6 days , then how many more days will be require for completing the remaining work ?
8
14
9
7
The correct Answer is:A
To solve the problem step by step, we can follow these instructions:
Step 1: Understand the total work done
The man completes 37 of the work in 6 days.
Step 2: Determine the total work
Let the total work be represented as 7x. This means that 37 of the total work is 3x.
Step 3: Calculate the remaining work
The remaining work can be calculated as:
Remaining work=Total work−Work done=7x−3x=4x
Step 4: Find the rate of work
Since the man completes 3x in 6 days, we can find the rate of work per day:
Rate of work=3x6=x2 (work per day)
Step 5: Calculate the time required to complete the remaining work
To find out how many days it will take to complete the remaining work 4x:
Days required=Remaining workRate of work=4xx2=4x×2x=8 days
Conclusion
Thus, the man will require 8 more days to complete the remaining work.
---
The man completes 37 of the work in 6 days.
Let the total work be represented as 7x. This means that 37 of the total work is 3x.
The remaining work can be calculated as:
Remaining work=Total work−Work done=7x−3x=4x
Since the man completes 3x in 6 days, we can find the rate of work per day:
Rate of work=3x6=x2 (work per day)
To find out how many days it will take to complete the remaining work 4x:
Days required=Remaining workRate of work=4xx2=4x×2x=8 days
Thus, the man will require 8 more days to complete the remaining work.
Similar Questions
Knowledge Check
- Question 1 - Select One
20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?
A8B10C15D20 - Question 2 - Select One
20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?
AA) 8BB) 10CC) 15DD) 20 - Question 3 - Select One
A work can be completed by 18 boys in 24 days. If 6 boys leave after working for 12 days, how many days will be needed to complete the remaining work?
A12B15C18D24
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View SolutionA work can be completed by 18 boys in 24 days. If 6 boys leave after working for 12 days, how many days will be needed to complete the remaining work?
View SolutionThe working capacity of A is 50% more than that of B. If A can complete a work in 12 days, then in how many days B will complete this work?
View SolutionA and B can complete a work in 8 days B & C can complete that work in 12 days and C and A completes that work in 8 days. Accordingly, in how many days all the three can complete that work ?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View Solution