If a man completes 37 work in 6 days , then how many more days will be require for completing the remaining work ?

A

8

B

14

C

9

D

7

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these instructions:

Step 1: Understand the total work done
The man completes 37 of the work in 6 days.

Step 2: Determine the total work
Let the total work be represented as 7x. This means that 37 of the total work is 3x.

Step 3: Calculate the remaining work
The remaining work can be calculated as:
Remaining work=Total workWork done=7x3x=4x

Step 4: Find the rate of work
Since the man completes 3x in 6 days, we can find the rate of work per day:
Rate of work=3x6=x2 (work per day)

Step 5: Calculate the time required to complete the remaining work
To find out how many days it will take to complete the remaining work 4x:
Days required=Remaining workRate of work=4xx2=4x×2x=8 days

Conclusion
Thus, the man will require 8 more days to complete the remaining work.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

    A8
    B10
    C15
    D20
  • Question 2 - Select One

    20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

    AA) 8
    BB) 10
    CC) 15
    DD) 20
  • Question 3 - Select One

    A work can be completed by 18 boys in 24 days. If 6 boys leave after working for 12 days, how many days will be needed to complete the remaining work?

    A12
    B15
    C18
    D24