A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
6
8
5
4
The correct Answer is:C
To solve the problem step by step, we can follow these instructions:
Step 1: Determine the work done by A and B in one day.
- A completes the work in 12 days, so A's work in one day is:
Work done by A in 1 day=112
- B completes the work in 15 days, so B's work in one day is:
Work done by B in 1 day=115
Hint: To find the work done in one day, take the reciprocal of the number of days taken to complete the work.
Step 2: Calculate the work done by A in the first 3 days.
- In 3 days, A will complete:
Work done by A in 3 days=3×112=312=14
Hint: Multiply the work done in one day by the number of days worked to find the total work done.
Step 3: Determine the remaining work after A has worked for 3 days.
- The total work is considered as 1 (whole work). Therefore, the remaining work after A has worked for 3 days is:
Remaining work=1−14=34
Hint: Subtract the work done from the total work to find the remaining work.
Step 4: Calculate the combined work done by A and B in one day.
- When A and B work together, their combined work in one day is:
Combined work=112+115
- To add these fractions, find the least common multiple (LCM) of 12 and 15, which is 60:
112=560,115=460
- Therefore,
Combined work=560+460=960=320
Hint: To add fractions, convert them to have a common denominator.
Step 5: Calculate the number of days required to complete the remaining work.
- Let X be the number of days required to finish the remaining work of 34:
X×320=34
- To find X, solve the equation:
X=3/43/20=34×203=204=5
Hint: To isolate X, divide the remaining work by the combined work done in one day.
Conclusion
- A and B together will take 5 days to complete the remaining work.
Final Answer: 5 days
- A completes the work in 12 days, so A's work in one day is:
Work done by A in 1 day=112
- B completes the work in 15 days, so B's work in one day is:
Work done by B in 1 day=115
- In 3 days, A will complete:
Work done by A in 3 days=3×112=312=14
- The total work is considered as 1 (whole work). Therefore, the remaining work after A has worked for 3 days is:
Remaining work=1−14=34
- When A and B work together, their combined work in one day is:
Combined work=112+115
- To add these fractions, find the least common multiple (LCM) of 12 and 15, which is 60:
112=560,115=460
- Therefore,
Combined work=560+460=960=320
- Let X be the number of days required to finish the remaining work of 34:
X×320=34
- To find X, solve the equation:
X=3/43/20=34×203=204=5
- A and B together will take 5 days to complete the remaining work.
Topper's Solved these Questions
- AVERAGE BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - AVERAGE EXERCISE - SELF ASSESSMENT SHEET -16
10 Videos
- ALGEBRIC IDENTITIESBOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - ALGEBRIC IDENTITIESEXERCISE - Self Assessment Sheet-7
10 Videos
- CIRCLES BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - CIRCLES EXERCISE - UNIT TEST
20 Videos
Similar Questions
45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
A6B8C5D4A completes a work in 15 days. B completes the same work in 20 days. A started working alone after 1 day B joined him. How many days will they now take together to complete the remaining work ?
A8 daysB7 daysC6 daysDNone of theseP can complete a work in 15 days.Q can complete the same work in 10 days ,P started working and after 5 days Q joined him. How many days more will they take to complete the remaining work ?
A1 daysB2 daysC3 daysD4 days
45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution