14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?

A

9 days

B

5 days

C

6 days

D

7 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for 14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?

    A6 days
    B8 days
    C623 days
    D734 days
  • Three men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?

    A1 days
    B2 days
    C3 days
    D4 days
  • 12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

    A10 days
    B12 days
    C15 days
    D9 days