3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys finish it in 6 days. 2 men and 4 boys will finish it in…..

A

9 days

B

10 days

C

12 days

D

14 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first define our variables and then set up equations based on the information given.

Step 1: Define Variables
Let:
- x = work done by 1 man in 1 day
- y = work done by 1 boy in 1 day

Step 2: Set Up Equations
From the problem, we have two scenarios:

1. 3 men and 4 boys do the work in 8 days:
The total work done can be expressed as:
8×(3x+4y)=Total Work

2. 4 men and 4 boys finish it in 6 days:
The total work done can also be expressed as:
6×(4x+4y)=Total Work

Since both expressions equal the total work, we can set them equal to each other:
8(3x+4y)=6(4x+4y)

Step 3: Simplify the Equation
Expanding both sides:
24x+32y=24x+24y

Now, subtract 24x from both sides:
32y=24y

Step 4: Solve for y
Subtract 24y from both sides:
32y24y=0
8y=0y=0

Step 5: Substitute y Back to Find x
Now we can substitute y=0 back into one of the original equations. Let's use the first one:
8(3x+4(0))=Total Work
This simplifies to:
24x=Total Work

Step 6: Find Total Work from the Second Equation
Using the second equation:
6(4x+4(0))=Total Work
This simplifies to:
24x=Total Work

Step 7: Calculate Work Done by 2 Men and 4 Boys
Now we need to find out how long it will take for 2 men and 4 boys to finish the work:
Work done by 2 men and 4 boys in 1 day=2x+4y=2x+4(0)=2x

Step 8: Calculate the Days Required
The total work is 24x, and the work done in one day by 2 men is 2x:
Days required=Total WorkWork done in 1 day=24x2x=12 days

Final Answer
Thus, 2 men and 4 boys will finish the work in 12 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

    A2 days
    B4 days
    C6 days
    D16 days
  • 2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in:

    A21 days
    B18 days
    C24 days
    D36 days
  • 2 men and 4 boys can complete a work in 10 days where as 4 men and 5 boys can complete it in 6 days. These men and boys get their wages according to their work. According, if per day wages of a man is ₹ 40, then find the ratio of per day wages of 1 man and 1 boy?

    A7:4
    B7:3
    C5:3
    D5:2