3 men and 4 boys do a piece of work in 8 days, while 4 men and 4 boys finish it in 6 days. 2 men and 4 boys will finish it in…..
9 days
10 days
12 days
14 days
The correct Answer is:C
To solve the problem step by step, we will first define our variables and then set up equations based on the information given.
Step 1: Define Variables
Let:
- x = work done by 1 man in 1 day
- y = work done by 1 boy in 1 day
Step 2: Set Up Equations
From the problem, we have two scenarios:
1. 3 men and 4 boys do the work in 8 days:
The total work done can be expressed as:
8×(3x+4y)=Total Work
2. 4 men and 4 boys finish it in 6 days:
The total work done can also be expressed as:
6×(4x+4y)=Total Work
Since both expressions equal the total work, we can set them equal to each other:
8(3x+4y)=6(4x+4y)
Step 3: Simplify the Equation
Expanding both sides:
24x+32y=24x+24y
Now, subtract 24x from both sides:
32y=24y
Step 4: Solve for y
Subtract 24y from both sides:
32y−24y=0
8y=0⟹y=0
Step 5: Substitute y Back to Find x
Now we can substitute y=0 back into one of the original equations. Let's use the first one:
8(3x+4(0))=Total Work
This simplifies to:
24x=Total Work
Step 6: Find Total Work from the Second Equation
Using the second equation:
6(4x+4(0))=Total Work
This simplifies to:
24x=Total Work
Step 7: Calculate Work Done by 2 Men and 4 Boys
Now we need to find out how long it will take for 2 men and 4 boys to finish the work:
Work done by 2 men and 4 boys in 1 day=2x+4y=2x+4(0)=2x
Step 8: Calculate the Days Required
The total work is 24x, and the work done in one day by 2 men is 2x:
Days required=Total WorkWork done in 1 day=24x2x=12 days
Final Answer
Thus, 2 men and 4 boys will finish the work in 12 days.
---
Let:
- x = work done by 1 man in 1 day
- y = work done by 1 boy in 1 day
From the problem, we have two scenarios:
The total work done can be expressed as:
8×(3x+4y)=Total Work
The total work done can also be expressed as:
6×(4x+4y)=Total Work
8(3x+4y)=6(4x+4y)
Expanding both sides:
24x+32y=24x+24y
32y=24y
Subtract 24y from both sides:
32y−24y=0
8y=0⟹y=0
Now we can substitute y=0 back into one of the original equations. Let's use the first one:
8(3x+4(0))=Total Work
This simplifies to:
24x=Total Work
Using the second equation:
6(4x+4(0))=Total Work
This simplifies to:
24x=Total Work
Now we need to find out how long it will take for 2 men and 4 boys to finish the work:
Work done by 2 men and 4 boys in 1 day=2x+4y=2x+4(0)=2x
The total work is 24x, and the work done in one day by 2 men is 2x:
Days required=Total WorkWork done in 1 day=24x2x=12 days
Thus, 2 men and 4 boys will finish the work in 12 days.
Topper's Solved these Questions
Similar Questions
4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is
View Solution8 men and 12 boys can finish a piece of work in 5 days, while 6 men and 8 boys can finish it in 7 days. Find the time taken by 1 man along and that by 1 boy alone to finish the work.
View Solution
Knowledge Check
If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in
A2 daysB4 daysC6 daysD16 days2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in:
A21 daysB18 daysC24 daysD36 days2 men and 4 boys can complete a work in 10 days where as 4 men and 5 boys can complete it in 6 days. These men and boys get their wages according to their work. According, if per day wages of a man is ₹ 40, then find the ratio of per day wages of 1 man and 1 boy?
A7:4B7:3C5:3D5:2
8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.
View Solution2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.
View SolutionIf 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be 4 days b. 5 days c. 6 days d. 7 days
View SolutionIf 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution2 men and 3 women can finish a piece of work in 10 days, while 4 men can do it in 10 days. In how many days will 3 men and 3 women finish it ?
View Solution