A piec of work can be done by 12 men in 24 days. They started the work and after 4 days then 6 more men joined them. How many days will they all take to complete the remaining work ?

A

1213

B

1313

C

1123

D

1323

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B


(i) The work of 12 men in 4 days. =16
(ii) After four days, 12 men can do remaining work in (24-4) days.
M1=12andD1=20
(iii) M2=(12+6), find D2 by using M1D1=M2D2 .

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A piec of work can be done by 12 men in 24 days. They started the work and after 4 days then 6 more men joined them. How many days will they all take to complete the remaining work ?

    A1213
    B1313
    C1123
    D1323
  • 16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?

    A4 days
    B6 days
    C8 days
    D10 days
  • 16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?

    A4
    B6
    C8
    D10