Directions: In the following question, two quantities I and II are given. Compare both the quantities and choose the correct option and give answer accordingly.
Quantity I: A and B can do a work in 83 days, B and C can do the same work in 3 days, and A and C can do the same work in 245 days. In what time can C alone complete the work?
Quantity II: 15
Quantity I > Quantity II
Quantity I ≤ Quantity II
Quantity I < Quantity II
Quantity I ≥ Quantity II
The correct Answer is:C
To solve the problem, we need to determine how long C alone can complete the work based on the information given about A, B, and C working together.
1. Understanding the Work Rates:
- Let the total work be represented in units. We can assume the total work is 24 units for easier calculations (as it is a common multiple of the denominators).
2. Calculate Work Rates:
- A + B can complete the work in 83 days:
Work rate of A + B=24 units83 days=24×38=9 units/day
- B + C can complete the work in 3 days:
Work rate of B + C=24 units3 days=8 units/day
- A + C can complete the work in 245 days:
Work rate of A + C=24 units245 days=24×524=5 units/day
3. Setting Up Equations:
- Let the work rates of A, B, and C be a, b, and c respectively.
- From the work rates calculated:
- a+b=9 (1)
- b+c=8 (2)
- a+c=5 (3)
4. Solving the Equations:
- From equation (1), we have a=9−b.
- Substitute a in equation (3):
(9−b)+c=5⟹c=5−9+b⟹c=b−4(4)
- Substitute c from equation (4) into equation (2):
b+(b−4)=8⟹2b−4=8⟹2b=12⟹b=6
- Substitute b=6 back into equations (1) and (4):
a+6=9⟹a=3
c=6−4=2
5. Finding C's Work Rate:
- C can complete 2 units of work in one day. To find out how many days C will take to complete the total work of 24 units:
Time taken by C=24 units2 units/day=12 days
Conclusion:
- Quantity I: C can complete the work in 12 days.
- Quantity II: 15 days.
Comparison:
- Since 12 days (Quantity I) is less than 15 days (Quantity II), we conclude that Quantity I is smaller than Quantity II.
Final Answer:
- Quantity I is less than Quantity II.
---
- Let the total work be represented in units. We can assume the total work is 24 units for easier calculations (as it is a common multiple of the denominators).
2. Calculate Work Rates:
- A + B can complete the work in 83 days:
Work rate of A + B=24 units83 days=24×38=9 units/day
- B + C can complete the work in 3 days:
Work rate of B + C=24 units3 days=8 units/day
- A + C can complete the work in 245 days:
Work rate of A + C=24 units245 days=24×524=5 units/day
- Let the work rates of A, B, and C be a, b, and c respectively.
- From the work rates calculated:
- a+b=9 (1)
- b+c=8 (2)
- a+c=5 (3)
- From equation (1), we have a=9−b.
- Substitute a in equation (3):
(9−b)+c=5⟹c=5−9+b⟹c=b−4(4)
- Substitute c from equation (4) into equation (2):
b+(b−4)=8⟹2b−4=8⟹2b=12⟹b=6
- Substitute b=6 back into equations (1) and (4):
a+6=9⟹a=3
c=6−4=2
- C can complete 2 units of work in one day. To find out how many days C will take to complete the total work of 24 units:
Time taken by C=24 units2 units/day=12 days
- Quantity I: C can complete the work in 12 days.
- Quantity II: 15 days.
- Since 12 days (Quantity I) is less than 15 days (Quantity II), we conclude that Quantity I is smaller than Quantity II.
- Quantity I is less than Quantity II.
Similar Questions
A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View SolutionA and B can do a certain work in 12 days, B & C can do the same work in 15 days, while A and C can do the same work in 36 days. In how many days will all three together complete that work ?
View Solution
Knowledge Check
A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?
A120 daysB118 daysC115 daysD110 daysB and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?
A14B134/11C144/13D12A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is
A5 daysB10 daysC15 daysD20 days
A and B can do a work in 8 days. B alone can do it in 24 days. In how many days, A alone can do the same work?
View SolutionA and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View SolutionA and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is
View SolutionA and B can do a work in 30 days, B and C can do it in 36 days and C and A can do the same work in 45 days. In how many days A, B and C can do this work together?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?
View Solution