Directions: In the following question, two quantities I and II are given. Compare both the quantities and choose the correct option and give answer accordingly.
Quantity I: A and B can do a work in 83 days, B and C can do the same work in 3 days, and A and C can do the same work in 245 days. In what time can C alone complete the work?
Quantity II: 15

A

Quantity I > Quantity II

B

Quantity I Quantity II

C

Quantity I < Quantity II

D

Quantity I Quantity II

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how long C alone can complete the work based on the information given about A, B, and C working together.

1. Understanding the Work Rates:
- Let the total work be represented in units. We can assume the total work is 24 units for easier calculations (as it is a common multiple of the denominators).

2. Calculate Work Rates:
- A + B can complete the work in 83 days:
Work rate of A + B=24 units83 days=24×38=9 units/day
- B + C can complete the work in 3 days:
Work rate of B + C=24 units3 days=8 units/day
- A + C can complete the work in 245 days:
Work rate of A + C=24 units245 days=24×524=5 units/day

3. Setting Up Equations:
- Let the work rates of A, B, and C be a, b, and c respectively.
- From the work rates calculated:
- a+b=9 (1)
- b+c=8 (2)
- a+c=5 (3)

4. Solving the Equations:
- From equation (1), we have a=9b.
- Substitute a in equation (3):
(9b)+c=5c=59+bc=b4(4)
- Substitute c from equation (4) into equation (2):
b+(b4)=82b4=82b=12b=6
- Substitute b=6 back into equations (1) and (4):
a+6=9a=3
c=64=2

5. Finding C's Work Rate:
- C can complete 2 units of work in one day. To find out how many days C will take to complete the total work of 24 units:
Time taken by C=24 units2 units/day=12 days

Conclusion:
- Quantity I: C can complete the work in 12 days.
- Quantity II: 15 days.

Comparison:
- Since 12 days (Quantity I) is less than 15 days (Quantity II), we conclude that Quantity I is smaller than Quantity II.

Final Answer:
- Quantity I is less than Quantity II.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

    A120 days
    B118 days
    C115 days
    D110 days
  • B and C can do a work in 12 days. C and D can do the same work in 18 days. D and B can do the same work in 24 days. In how many days can B, C and D together complete the work?

    A14
    B134/11
    C144/13
    D12
  • A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

    A5 days
    B10 days
    C15 days
    D20 days