A contractor has the target of completing a work in 40 days . He employed 20 persons who completed (1/4) of the work in 10 days and left. The number of persons he has to employ to finish the remaining part as per target is :
20
40
30
10
The correct Answer is:A
To solve the problem step by step, we will use the concept of work done, which can be expressed in terms of the number of men, the number of days they work, and the fraction of work completed.
Step 1: Determine the total work done by the initial group of workers.
The contractor employed 20 persons who completed 14 of the work in 10 days.
Work done (W1) = 14
Step 2: Calculate the total work in terms of man-days.
Since 20 persons worked for 10 days, the total man-days used is:
Man-days=Number of persons×Number of days=20×10=200 man-days
Step 3: Calculate the total work.
If 14 of the work corresponds to 200 man-days, then the total work (W) can be calculated as follows:
W=Total work=200 man-days×4=800 man-days
Step 4: Determine the remaining work.
Since 14 of the work is completed, the remaining work is:
Remaining work=W−14W=34W=34×800=600 man-days
Step 5: Calculate the number of days left to complete the work.
The total target time is 40 days, and 10 days have already been used, so the remaining time (D2) is:
D2=40−10=30 days
Step 6: Use the work formula to find the number of workers needed.
Using the relationship:
M1×D1=M2×D2
Where:
- M1=20 (initial workers)
- D1=10 (days worked)
- W1=14W (work done)
- M2 is the number of workers needed to finish the remaining work in 30 days.
We can express this as:
20×10=M2×30
Step 7: Solve for M2.
200=M2×30
M2=20030=203≈6.67
Since we cannot have a fraction of a worker, we round up to the nearest whole number:
M2=7
Final Answer:
The contractor needs to employ 7 persons to finish the remaining work in the allotted time.
The contractor employed 20 persons who completed 14 of the work in 10 days.
Since 20 persons worked for 10 days, the total man-days used is:
Man-days=Number of persons×Number of days=20×10=200 man-days
If 14 of the work corresponds to 200 man-days, then the total work (W) can be calculated as follows:
W=Total work=200 man-days×4=800 man-days
Since 14 of the work is completed, the remaining work is:
Remaining work=W−14W=34W=34×800=600 man-days
The total target time is 40 days, and 10 days have already been used, so the remaining time (D2) is:
D2=40−10=30 days
Using the relationship:
M1×D1=M2×D2
Where:
- M1=20 (initial workers)
- D1=10 (days worked)
- W1=14W (work done)
- M2 is the number of workers needed to finish the remaining work in 30 days.
20×10=M2×30
200=M2×30
M2=20030=203≈6.67
M2=7
The contractor needs to employ 7 persons to finish the remaining work in the allotted time.
Similar Questions
Knowledge Check
25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
A120B125C100D21520 persons completed 13rd of the work in 12 days. How many more person are required to finish rest work in next 12 days?
A20B12C18D4020 persons completed 13rd of the work in 24 days. How many more person are required to finish the rest of the work in next 12 days?
A20B12C18D40
If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View SolutionIf 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
View Solution35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is
View SolutionA contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View Solution