A work is done by 30 workers not all of them have the same capacity to work. Every day exactly 2 workers, do the work with no pair of workers working together twice. Even after all possible pairs have worked once, all the workers together works for two more days to finish the work. Find the number of days in which all the workers together will finish the whole work?

A

31

B

29

C

41

D

48

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will break down the information given and derive the solution systematically.

Step 1: Understanding the Problem
We have 30 workers, and they work in pairs. Each day, exactly 2 workers work together, and no pair of workers works together more than once. After all possible pairs have worked, the workers work together for 2 more days to finish the work.

Step 2: Calculate the Number of Unique Pairs
The total number of ways to choose 2 workers from 30 is given by the combination formula:
Number of pairs=(302)=30×292=435
This means there are 435 unique pairs of workers.

Step 3: Determine the Total Days of Pair Work
Since each day only one pair works, the number of days they can work with all unique pairs is 435 days.

Step 4: Total Work Done by Pairs
The total work done by all pairs in 435 days is equivalent to the work done in one day by all workers working together. If we denote the total work done by the pairs in one day as W, then:
Total work done by pairs=435×W

Step 5: Work Done in the Last Two Days
After all pairs have worked, the workers work together for 2 more days. Let’s denote the work done by all workers in one day as Wtotal. Therefore, the work done in the last two days is:
Work done in last 2 days=2×Wtotal

Step 6: Total Work Calculation
The total work done is the sum of the work done by pairs and the work done in the last two days:
Total Work=435×W+2×Wtotal

Step 7: Equating Total Work
Since the total work can also be expressed as the work done by all 30 workers working together for D days:
Total Work=D×Wtotal

Step 8: Setting Up the Equation
Equating the two expressions for total work, we have:
D×Wtotal=435×W+2×Wtotal

Step 9: Solve for D
Rearranging the equation gives:
D×Wtotal2×Wtotal=435×W
Factoring out Wtotal:
Wtotal(D2)=435×W
Thus, we can express D as:
D=435×WWtotal+2

Step 10: Finding the Value of D
Given that the efficiency of the workers is equal, we can assume Wtotal is the total efficiency of all workers. Hence, if we denote the work done by each worker as equal, we can find that:
D=31

Conclusion
Thus, the total number of days in which all the workers together will finish the whole work is 31 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A Works twice as fast as B. If B can complete a work in 12 days independently. The number of days in which A and B can together finish the work is :

    A4 days
    B6 days
    C8 days
    D18 days
  • 150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • A can do in one day three times the work done by B in one day. They together finish 25 of the work in 9 days. The number of days by which B can do the work alone is :

    A90 days
    B120 days
    C100 days
    D30 days