Aditya, Vedus and Yuvraj alone can do a job for 6 weeks, 9 weeks and 12 weeks respectively. They work together for 2 weeks. Then, Aditya leaves the job. Vedus leaves the job a week earlier to the completion of the work. The job would be completed in:

A

4 weeks

B

5 weeks

C

7 weeks

D

None of these

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step-by-step, let's break it down:

Step 1: Determine the work done by each person in one week.
- Aditya's work rate: He can complete the job in 6 weeks, so his work rate is 16 of the job per week.
- Vedus's work rate: He can complete the job in 9 weeks, so his work rate is 19 of the job per week.
- Yuvraj's work rate: He can complete the job in 12 weeks, so his work rate is 112 of the job per week.

Step 2: Calculate the combined work rate when all three work together.
- Combined work rate = 16+19+112

To add these fractions, we need a common denominator. The least common multiple (LCM) of 6, 9, and 12 is 36.

- Convert each fraction:
- 16=636
- 19=436
- 112=336

Now, add them together:
636+436+336=1336

Step 3: Calculate the total work done in 2 weeks.
- Work done in 2 weeks = 2×1336=2636=1318 of the job.

Step 4: Determine the remaining work.
- Total work = 1 (the whole job).
- Remaining work = 11318=518 of the job.

Step 5: Determine who works next and their work rates.
- After 2 weeks, Aditya leaves. Now, Vedus and Yuvraj will work together.
- Combined work rate of Vedus and Yuvraj = 19+112

Convert these fractions to a common denominator:
- LCM of 9 and 12 is 36.
- Convert:
- 19=436
- 112=336

Combined work rate = 436+336=736

Step 6: Calculate the work done by Vedus and Yuvraj in 1 week.
- Work done in 1 week = 736.

Step 7: Determine the remaining work after Vedus leaves.
- Vedus leaves a week earlier, so they work together for 1 week.
- Work done in 1 week = 736.
- Remaining work = 518736.

Convert 518 to a fraction with a denominator of 36:
- 518=1036.

Now, calculate remaining work:
1036736=336=112

Step 8: Determine how long Yuvraj will take to finish the remaining work.
- Yuvraj's work rate is 112.
- Time taken to finish 112 of the job = 1/121/12=1 week.

Step 9: Calculate the total time taken to complete the job.
- Total time = 2 weeks (initial work) + 1 week (Vedus and Yuvraj) + 1 week (Yuvraj alone) = 4 weeks.

Final Answer:
The job would be completed in 4 weeks.

---

|


Similar Questions


Knowledge Check

  • A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?

    A9
    B6
    C12
    D10
  • A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is

    A556 days
    B514 days
    C312 days
    D334 days
  • A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

    A20
    B30
    C18
    D24