Aditya, Vedus and Yuvraj alone can do a job for 6 weeks, 9 weeks and 12 weeks respectively. They work together for 2 weeks. Then, Aditya leaves the job. Vedus leaves the job a week earlier to the completion of the work. The job would be completed in:
4 weeks
5 weeks
7 weeks
None of these
The correct Answer is:A
To solve the problem step-by-step, let's break it down:
Step 1: Determine the work done by each person in one week.
- Aditya's work rate: He can complete the job in 6 weeks, so his work rate is 16 of the job per week.
- Vedus's work rate: He can complete the job in 9 weeks, so his work rate is 19 of the job per week.
- Yuvraj's work rate: He can complete the job in 12 weeks, so his work rate is 112 of the job per week.
Step 2: Calculate the combined work rate when all three work together.
- Combined work rate = 16+19+112
To add these fractions, we need a common denominator. The least common multiple (LCM) of 6, 9, and 12 is 36.
- Convert each fraction:
- 16=636
- 19=436
- 112=336
Now, add them together:
636+436+336=1336
Step 3: Calculate the total work done in 2 weeks.
- Work done in 2 weeks = 2×1336=2636=1318 of the job.
Step 4: Determine the remaining work.
- Total work = 1 (the whole job).
- Remaining work = 1−1318=518 of the job.
Step 5: Determine who works next and their work rates.
- After 2 weeks, Aditya leaves. Now, Vedus and Yuvraj will work together.
- Combined work rate of Vedus and Yuvraj = 19+112
Convert these fractions to a common denominator:
- LCM of 9 and 12 is 36.
- Convert:
- 19=436
- 112=336
Combined work rate = 436+336=736
Step 6: Calculate the work done by Vedus and Yuvraj in 1 week.
- Work done in 1 week = 736.
Step 7: Determine the remaining work after Vedus leaves.
- Vedus leaves a week earlier, so they work together for 1 week.
- Work done in 1 week = 736.
- Remaining work = 518−736.
Convert 518 to a fraction with a denominator of 36:
- 518=1036.
Now, calculate remaining work:
1036−736=336=112
Step 8: Determine how long Yuvraj will take to finish the remaining work.
- Yuvraj's work rate is 112.
- Time taken to finish 112 of the job = 1/121/12=1 week.
Step 9: Calculate the total time taken to complete the job.
- Total time = 2 weeks (initial work) + 1 week (Vedus and Yuvraj) + 1 week (Yuvraj alone) = 4 weeks.
Final Answer:
The job would be completed in 4 weeks.
---
- Aditya's work rate: He can complete the job in 6 weeks, so his work rate is 16 of the job per week.
- Vedus's work rate: He can complete the job in 9 weeks, so his work rate is 19 of the job per week.
- Yuvraj's work rate: He can complete the job in 12 weeks, so his work rate is 112 of the job per week.
- Combined work rate = 16+19+112
- 16=636
- 19=436
- 112=336
636+436+336=1336
- Work done in 2 weeks = 2×1336=2636=1318 of the job.
- Total work = 1 (the whole job).
- Remaining work = 1−1318=518 of the job.
- After 2 weeks, Aditya leaves. Now, Vedus and Yuvraj will work together.
- Combined work rate of Vedus and Yuvraj = 19+112
- LCM of 9 and 12 is 36.
- Convert:
- 19=436
- 112=336
- Work done in 1 week = 736.
- Vedus leaves a week earlier, so they work together for 1 week.
- Work done in 1 week = 736.
- Remaining work = 518−736.
- 518=1036.
1036−736=336=112
- Yuvraj's work rate is 112.
- Time taken to finish 112 of the job = 1/121/12=1 week.
- Total time = 2 weeks (initial work) + 1 week (Vedus and Yuvraj) + 1 week (Yuvraj alone) = 4 weeks.
The job would be completed in 4 weeks.
Similar Questions
A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View Solution
Knowledge Check
A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?
A9B6C12D10A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
A556 daysB514 daysC312 daysD334 daysA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
A20B30C18D24
A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 18 of the work is completed, C leaves the job. Rest of the work is done by A and B together. Time taken to finish the remaining work is
View SolutionIf A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?
View SolutionAshish, Binay and Joseph can do a job in 20, 30 and 40 days respectively. The three started the job together, Ashish left the job 4 days before it was completed and Binay left the job 3 days before it was completed. In how many days was the job completed?
View SolutionCan he complete the job in three weeks?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View Solution