A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, It would have taken them four days to complete the job. How much time would it take for A alone to do the work?
10 days
20 days
25 days
15 days
The correct Answer is:A
To solve the problem, we need to determine how much time A alone would take to complete the work. Let's break down the steps:
Step 1: Define the total work
Let's assume the total work is 100 units.
Step 2: Calculate the combined work rate of A and B
Since A and B complete the work together in 5 days, their combined work rate is:
Work rate of A and B=100 units5 days=20 units per day
Step 3: Set up the equations for the modified speeds
If A works at twice his speed and B works at half his speed, let's denote the work rates of A and B as a and b respectively. Therefore, we have:
a+b=20(1)
When A's speed is doubled and B's speed is halved, their new work rates become 2a and b2. They complete the work in 4 days, so:
2a+b2=100 units4 days=25 units per day
This gives us the second equation:
2a+b2=25(2)
Step 4: Solve the equations
From equation (1), we can express b in terms of a:
b=20−a(3)
Substituting equation (3) into equation (2):
2a+20−a2=25
Multiplying through by 2 to eliminate the fraction:
4a+20−a=50
Combining like terms:
3a+20=50
Subtracting 20 from both sides:
3a=30
Dividing by 3:
a=10
Step 5: Find the value of b
Using equation (3):
b=20−a=20−10=10
Step 6: Calculate the time taken by A alone
Now that we have a=10 (the work rate of A), we can find the time taken by A to complete the work alone:
Time taken by A=100 unitsa=10010=10 days
Final Answer
A alone would take 10 days to complete the work.
---
Let's assume the total work is 100 units.
Since A and B complete the work together in 5 days, their combined work rate is:
Work rate of A and B=100 units5 days=20 units per day
If A works at twice his speed and B works at half his speed, let's denote the work rates of A and B as a and b respectively. Therefore, we have:
a+b=20(1)
When A's speed is doubled and B's speed is halved, their new work rates become 2a and b2. They complete the work in 4 days, so:
2a+b2=100 units4 days=25 units per day
This gives us the second equation:
2a+b2=25(2)
From equation (1), we can express b in terms of a:
b=20−a(3)
Substituting equation (3) into equation (2):
2a+20−a2=25
Multiplying through by 2 to eliminate the fraction:
4a+20−a=50
Combining like terms:
3a+20=50
Subtracting 20 from both sides:
3a=30
Dividing by 3:
a=10
Using equation (3):
b=20−a=20−10=10
Now that we have a=10 (the work rate of A), we can find the time taken by A to complete the work alone:
Time taken by A=100 unitsa=10010=10 days
A alone would take 10 days to complete the work.
Similar Questions
If A & B completed a work together in 6 days . If A completed the same work in 10 days alone . Then in how many days will B complete the same work alone ?
View SolutionA and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View Solution
Knowledge Check
A and B completed a work together in 8 days. Had A worked at twice the speed and B at one-third of his speed it would have taken them 6 days to complete the job. How much time would it take for B alone to do the work?
A10B20C15D25A certain work is completed by A and B together in 10 days.
If A had worked at twice the speed and B had worked at half
his speed it would have taken them 8 days to finish the
work. Find the time in which B can alone finish the work.A20 daysB24 daysC30 daysD32 daysA does half as much work as B in three fourth of the times. If together they take 18 days to complete the work, how much time shall B alone take to do it?
A50 daysB45 daysC40 daysD30 days
A, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?
View SolutionA does half as much work as B in three-fourth of the time. If together they take 18 days to complete a work, how much time shall B take to do it alone ?
View SolutionA does half as much work as B in three fourth of the times. If together they take 18 days to complete the work, how much time shall B alone take to do it?
View SolutionA does half as much work as B in three fourth of the times. If together they take 18 days to complete the work, how much time shall B alone take to do it?
View SolutionA and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View Solution