A, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?
30
22
20
45
To solve the problem, we need to determine how many days B would take to complete the task alone. We can start by finding the work rates of A, B, and C based on the information given.
Step 1: Determine the work rates of A, B, and C
1. A + B + C can complete the task in 10 days.
- Work rate of A + B + C = 1 task / 10 days = 1/10 tasks per day.
2. A + B can complete the task in 12 days.
- Work rate of A + B = 1 task / 12 days = 1/12 tasks per day.
3. B + C can complete the task in 20 days.
- Work rate of B + C = 1 task / 20 days = 1/20 tasks per day.
Step 2: Set up equations based on work rates
Let:
- Rate of A = a tasks per day
- Rate of B = b tasks per day
- Rate of C = c tasks per day
From the work rates, we can set up the following equations:
1. a+b+c=110 (Equation 1)
2. a+b=112 (Equation 2)
3. b+c=120 (Equation 3)
Step 3: Solve the equations
From Equation 2, we can express a in terms of b:
a=112−b (Equation 4)
Now, substitute Equation 4 into Equation 1:
(112−b)+b+c=110
This simplifies to:
112+c=110
Now, isolate c:
c=110−112
To subtract these fractions, find a common denominator (which is 60):
c=660−560=160
Step 4: Substitute c back to find b
Now substitute c back into Equation 3:
b+160=120
Isolate b:
b=120−160
Again, find a common denominator (which is 60):
b=360−160=260=130
Step 5: Find the time B would take to complete the task alone
Since b represents the work rate of B, we can find the time B would take to complete the task alone:
If B's rate is 130 tasks per day, then the time taken by B to complete 1 task is:
Time=1 taskb=1130=30 days
Final Answer
B would take 30 days to complete the task alone.
---
- Work rate of A + B + C = 1 task / 10 days = 1/10 tasks per day.
- Work rate of A + B = 1 task / 12 days = 1/12 tasks per day.
- Work rate of B + C = 1 task / 20 days = 1/20 tasks per day.
- Rate of A = a tasks per day
- Rate of B = b tasks per day
- Rate of C = c tasks per day
2. a+b=112 (Equation 2)
3. b+c=120 (Equation 3)
Similar Questions
A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
View SolutionA can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
View Solution
Knowledge Check
A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?
A10B13.75C12.5D11.25Working together A, B and C can complete a task in 12 days. A and B can do the task in 55 days and 66 days respectively if they worked alone. In how many days can C do the task if he worked alone?
A22B44C20D40A and B can together complete a tsk in 21 days. If a alone takes 42 days to complete the task, the number of days that B would take to do the task alone is :
A42B36C27D32
13.A and B together can do a work in 25days. They work to together for 15days and then B leaves.A finishes the rest of the work in 20 days.How many days would each take to complete the work seperately?
View SolutionPersons A, B and C can complete a task together in 81 days. A and B can complete the same task together in 97.2 days. B and C can complete the same task together in 162 days. In how many days can B alone complete the task?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionA can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View Solution