A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
10 days
12 days
15 days
16 days
The correct Answer is:C
Step by step video & text solution for A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.
View SolutionA can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a piece of work In 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
A10 daysB12 daysC15 daysD16 days - Question 2 - Select One
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB9 daysC10 daysD13 days - Question 3 - Select One
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A6 daysB8 daysC9 daysD5 days
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed ?
View SolutionWorking together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगेView SolutionA and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
View Solution