If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:
18 days
24 days
30 days
40 days
The correct Answer is:B
To solve the problem, we need to find out how long B alone can complete the work given the information about A and B, A and C, and B and C. Let's break it down step by step.
1. Understanding the Work Rates:
- Let the total work be represented as 1 unit of work.
- If A and B together can complete the work in 18 days, their combined work rate is:
Rate of (A + B)=118 work per day
- If A and C together can complete the work in 12 days, their combined work rate is:
Rate of (A + C)=112 work per day
- If B and C together can complete the work in 9 days, their combined work rate is:
Rate of (B + C)=19 work per day
2. Setting Up the Equations:
- Let the work rates of A, B, and C be represented as a,b, and c respectively. We can write the following equations based on the combined work rates:
a+b=118(1)
a+c=112(2)
b+c=19(3)
3. Adding the Equations:
- Now, we will add all three equations:
(a+b)+(a+c)+(b+c)=118+112+19
- This simplifies to:
2a+2b+2c=118+112+19
4. Finding a Common Denominator:
- The least common multiple (LCM) of 18, 12, and 9 is 36. We convert each fraction:
118=236,112=336,19=436
- Adding these gives:
236+336+436=936=14
5. Simplifying the Equation:
- Now we have:
2a+2b+2c=14
- Dividing everything by 2:
a+b+c=18(4)
6. Finding Individual Work Rates:
- Now we can find the individual work rates:
- From equation (1):
c=18−(a+b)=18−118
To subtract, we need a common denominator (LCM of 8 and 18 is 72):
c=972−472=572
- Substitute c back into equation (3):
b+572=19⇒b=19−572
Again, using LCM of 9 and 72 (which is 72):
b=872−572=372=124
7. Finding the Time for B Alone:
- Since b=124, this means B can complete the work alone in:
Time taken by B=1b=24 days
Final Answer:
B alone can complete the work in 24 days.
- Let the total work be represented as 1 unit of work.
- If A and B together can complete the work in 18 days, their combined work rate is:
Rate of (A + B)=118 work per day
Rate of (A + C)=112 work per day
Rate of (B + C)=19 work per day
- Let the work rates of A, B, and C be represented as a,b, and c respectively. We can write the following equations based on the combined work rates:
a+b=118(1)
a+c=112(2)
b+c=19(3)
- Now, we will add all three equations:
(a+b)+(a+c)+(b+c)=118+112+19
- This simplifies to:
2a+2b+2c=118+112+19
- The least common multiple (LCM) of 18, 12, and 9 is 36. We convert each fraction:
118=236,112=336,19=436
- Adding these gives:
236+336+436=936=14
- Now we have:
2a+2b+2c=14
- Dividing everything by 2:
a+b+c=18(4)
- Now we can find the individual work rates:
- From equation (1):
c=18−(a+b)=18−118
To subtract, we need a common denominator (LCM of 8 and 18 is 72):
c=972−472=572
b+572=19⇒b=19−572
Again, using LCM of 9 and 72 (which is 72):
b=872−572=372=124
- Since b=124, this means B can complete the work alone in:
Time taken by B=1b=24 days
B alone can complete the work in 24 days.
Similar Questions
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :
A334 daysB337 daysC5547 daysD449 days - Question 2 - Select One
A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
A80 daysB100 daysC120 daysD150 days - Question 3 - Select One
A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?
A12 daysB8 daysC14 daysD10 days
A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in
View SolutionA and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगेView SolutionA and B together can be do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work in how many days /
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
View Solution