Hemant and Vikash working together can make a wall in 15 days. They both started building the wall and after 3 days Hemant left and Vikash alone build the remaining wall in 24 more days. Find efficiency of Hemant is what percent of Vikash's.
0.5
0.2
0.25
1
The correct Answer is:D
To solve the problem step by step, let's break it down:
Step 1: Calculate the total work done by Hemant and Vikash together.
Hemant and Vikash can complete the wall together in 15 days. Therefore, the total work can be represented as:
Total Work=1 wall
Since they complete the wall in 15 days, their combined efficiency (work done per day) is:
Combined Efficiency=1 wall15 days=115 walls per day
Step 2: Calculate the work done in the first 3 days.
In the first 3 days, Hemant and Vikash work together. The work done in these 3 days is:
Work done in 3 days=3×Combined Efficiency=3×115=315=15 walls
Step 3: Calculate the remaining work.
After 3 days, the remaining work is:
Remaining Work=1−15=45 walls
Step 4: Calculate Vikash's efficiency.
Vikash completes the remaining 45 wall in 24 days. Therefore, Vikash's efficiency is:
Vikash's Efficiency=Remaining WorkTime taken=45 walls24 days=45×24=4120=130 walls per day
Step 5: Calculate Hemant's efficiency.
Let Hemant's efficiency be h. Since together their efficiency is 115:
h+130=115
To find h, we can rearrange the equation:
h=115−130
Finding a common denominator (which is 30):
h=230−130=130 walls per day
Step 6: Calculate the percentage of Hemant's efficiency compared to Vikash's.
Now we need to find what percent Hemant's efficiency is of Vikash's efficiency:
Percentage=(hVikash's Efficiency)×100
=⎛⎝130130⎞⎠×100=1×100=100%
Conclusion:
Hemant's efficiency is 100% of Vikash's efficiency.
Hemant and Vikash can complete the wall together in 15 days. Therefore, the total work can be represented as:
Total Work=1 wall
Combined Efficiency=1 wall15 days=115 walls per day
In the first 3 days, Hemant and Vikash work together. The work done in these 3 days is:
Work done in 3 days=3×Combined Efficiency=3×115=315=15 walls
After 3 days, the remaining work is:
Remaining Work=1−15=45 walls
Vikash completes the remaining 45 wall in 24 days. Therefore, Vikash's efficiency is:
Vikash's Efficiency=Remaining WorkTime taken=45 walls24 days=45×24=4120=130 walls per day
Let Hemant's efficiency be h. Since together their efficiency is 115:
h+130=115
h=115−130
h=230−130=130 walls per day
Now we need to find what percent Hemant's efficiency is of Vikash's efficiency:
Percentage=(hVikash's Efficiency)×100
=⎛⎝130130⎞⎠×100=1×100=100%
Hemant's efficiency is 100% of Vikash's efficiency.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
A can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View Solution
Knowledge Check
- Question 1 - Select One
14 workers can build a wall in 42 days. One worker can build it in
A3 dayB147 dayC294 dayD588 day - Question 2 - Select One
A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
A75B25C45D60 - Question 3 - Select One
A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
A21B24C28D32
A and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionRohan and Mohit together can build a wall in 8 days. Mohit and Vikas can build the same wall in 10 days and Vikas and Rohan can build the same wall in 12 days. In how many days can all the three complete the same wall while working together?
View Solution3 persons can build a wall in 4 days, then 4 persons can build it in
View SolutionA and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
View SolutionRaja and Kundan together can build a wall in 20 days, Kundan and Mahesh build the same wall in 30 days and Mahesh and Raja can build the same wall in 24 days. In how many days can all the three complete the same wall while working together?
View Solution