Hemant and Vikash working together can make a wall in 15 days. They both started building the wall and after 3 days Hemant left and Vikash alone build the remaining wall in 24 more days. Find efficiency of Hemant is what percent of Vikash's.

A

0.5

B

0.2

C

0.25

D

1

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, let's break it down:

Step 1: Calculate the total work done by Hemant and Vikash together.
Hemant and Vikash can complete the wall together in 15 days. Therefore, the total work can be represented as:
Total Work=1 wall

Since they complete the wall in 15 days, their combined efficiency (work done per day) is:
Combined Efficiency=1 wall15 days=115 walls per day

Step 2: Calculate the work done in the first 3 days.
In the first 3 days, Hemant and Vikash work together. The work done in these 3 days is:
Work done in 3 days=3×Combined Efficiency=3×115=315=15 walls

Step 3: Calculate the remaining work.
After 3 days, the remaining work is:
Remaining Work=115=45 walls

Step 4: Calculate Vikash's efficiency.
Vikash completes the remaining 45 wall in 24 days. Therefore, Vikash's efficiency is:
Vikash's Efficiency=Remaining WorkTime taken=45 walls24 days=45×24=4120=130 walls per day

Step 5: Calculate Hemant's efficiency.
Let Hemant's efficiency be h. Since together their efficiency is 115:
h+130=115

To find h, we can rearrange the equation:
h=115130

Finding a common denominator (which is 30):
h=230130=130 walls per day

Step 6: Calculate the percentage of Hemant's efficiency compared to Vikash's.
Now we need to find what percent Hemant's efficiency is of Vikash's efficiency:
Percentage=(hVikash's Efficiency)×100
=130130×100=1×100=100%

Conclusion:
Hemant's efficiency is 100% of Vikash's efficiency.

|
Updated on:18/9/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    14 workers can build a wall in 42 days. One worker can build it in

    A3 day
    B147 day
    C294 day
    D588 day
  • Question 2 - Select One

    A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?

    A75
    B25
    C45
    D60
  • Question 3 - Select One

    A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?

    A21
    B24
    C28
    D32