If 9 men or 15 women can do a piece of work in 18 days working 9 hours a day. How many days will it take to complete a work twice as large with 6 men and 8 women working together 6 hours a day?
22 days
27.5 days
45 days
22.5 days
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by men and women, then calculate the total work required for the larger task, and finally find out how long it will take for 6 men and 8 women to complete that work.
Step 1: Determine the efficiency of men and women
Given:
- 9 men can complete the work in 18 days working 9 hours a day.
- 15 women can complete the same work in the same time.
Total work done by men:
Total Work=Number of Men×Days×Hours per Day×Efficiency of Men
Let the efficiency of men be m.
Total Work=9×18×9×m=1458m
Total work done by women:
Let the efficiency of women be w.
Total Work=15×18×9×w=2430w
Since both expressions represent the same total work:
1458m=2430w
Dividing both sides by 486 gives:
3m=5w⇒mw=53
Step 2: Calculate total work for twice the amount
Since the work is now twice as large:
Total Work=2×1458m=2916m
Step 3: Calculate the combined efficiency of 6 men and 8 women
Using the ratio of efficiencies:
- Efficiency of 6 men: 6m
- Efficiency of 8 women: 8w
Now substituting w in terms of m:
w=3m5⇒8w=8×3m5=24m5
Combined efficiency of 6 men and 8 women:
Combined Efficiency=6m+24m5=30m+24m5=54m5
Step 4: Calculate the number of days required to complete the work
Let D be the number of days required to complete the work with 6 men and 8 women working 6 hours a day.
Total Work=Combined Efficiency×Days×Hours per Day
2916m=(54m5)×D×6
Now simplifying:
2916m=324mD5
Cancelling m from both sides (assuming m≠0):
2916=324D5
Multiplying both sides by 5:
14580=324D
Dividing both sides by 324:
D=14580324=45
Final Answer
The number of days required to complete the work is 45 days.
---
Given:
- 9 men can complete the work in 18 days working 9 hours a day.
- 15 women can complete the same work in the same time.
Total Work=Number of Men×Days×Hours per Day×Efficiency of Men
Let the efficiency of men be m.
Total Work=9×18×9×m=1458m
Let the efficiency of women be w.
Total Work=15×18×9×w=2430w
1458m=2430w
Dividing both sides by 486 gives:
3m=5w⇒mw=53
Since the work is now twice as large:
Total Work=2×1458m=2916m
Using the ratio of efficiencies:
- Efficiency of 6 men: 6m
- Efficiency of 8 women: 8w
w=3m5⇒8w=8×3m5=24m5
Combined Efficiency=6m+24m5=30m+24m5=54m5
Let D be the number of days required to complete the work with 6 men and 8 women working 6 hours a day.
Total Work=Combined Efficiency×Days×Hours per Day
2916m=(54m5)×D×6
2916m=324mD5
Cancelling m from both sides (assuming m≠0):
2916=324D5
Multiplying both sides by 5:
14580=324D
Dividing both sides by 324:
D=14580324=45
The number of days required to complete the work is 45 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS
15 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionIf 5 men or 9 women can do a piece of work in 19 days, then in how many days will 3 men and 6 women do the same work? 12 b. 15 c. 18 d. 21
View Solution
Knowledge Check
If 4 men or 6 women can do a piece of work in 12 days workIng 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?
A6 daysB7 daysC8 daysD10 daysIf 3 men or 6 boy, can do a piece of work in 10 days, working 7 hours a day; how many days will it take to complete a piece of work twice as large with 6 men and 2 boy. 1% 'irking together for 8 hours a day? 6 b. 9 c. 812 d. 712
A7 1/2 daysB8 1/2 daysC9 daysD6 days9 women con complete a piece of work in 19 days. How
many days will 18 women take to complete the same piece of
work ?A12 daysB6.5 daysC9 daysDNone of these
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View SolutionIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
View SolutionIf 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
View SolutionIf 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
View SolutionIf 12 men or 18 women can do a piece of work in 14 days, then how long will 8 men and 16 women take to finish the work ?
View Solution