A and B can complete a work in 20 days and A alone can finish that work in 30 days. In how many days B can complete the work?
The correct Answer is:60 days
To solve the problem step by step, we will use the information given about the work done by A and B.
Step 1: Determine the total work
We know that A and B together can complete the work in 20 days. To find the total work, we can use the formula:
Total Work=Work Rate×Time
Since A and B together can complete the work in 20 days, we can calculate the total work as follows:
Total Work=1 (work)×20 (days)=20 work units
Step 2: Determine A's work rate
A alone can finish the work in 30 days. Therefore, A's work rate (efficiency) can be calculated as:
A's Work Rate=1 (work)30 (days)=130 work units per day
Step 3: Determine the combined work rate of A and B
Since A and B together can complete the work in 20 days, their combined work rate is:
Combined Work Rate (A + B)=1 (work)20 (days)=120 work units per day
Step 4: Calculate B's work rate
Now, we can find B's work rate by subtracting A's work rate from the combined work rate:
B's Work Rate=Combined Work Rate−A's Work Rate
B's Work Rate=120−130
To perform this subtraction, we need a common denominator. The least common multiple of 20 and 30 is 60. Therefore, we convert the fractions:
120=360
130=260
Now, we can subtract:
B's Work Rate=360−260=160 work units per day
Step 5: Calculate the time taken by B to complete the work alone
To find out how many days B can complete the work alone, we use the formula:
Time=Total WorkB's Work Rate
Time=1 (work)160 (work units per day)=60 days
Final Answer
B can complete the work alone in 60 days.
---
We know that A and B together can complete the work in 20 days. To find the total work, we can use the formula:
Total Work=Work Rate×Time
Total Work=1 (work)×20 (days)=20 work units
A alone can finish the work in 30 days. Therefore, A's work rate (efficiency) can be calculated as:
A's Work Rate=1 (work)30 (days)=130 work units per day
Since A and B together can complete the work in 20 days, their combined work rate is:
Combined Work Rate (A + B)=1 (work)20 (days)=120 work units per day
Now, we can find B's work rate by subtracting A's work rate from the combined work rate:
B's Work Rate=Combined Work Rate−A's Work Rate
B's Work Rate=120−130
120=360
130=260
B's Work Rate=360−260=160 work units per day
To find out how many days B can complete the work alone, we use the formula:
Time=Total WorkB's Work Rate
Time=1 (work)160 (work units per day)=60 days
B can complete the work alone in 60 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - SOLVED EXAMPLE
10 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS
15 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?
View SolutionBy working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View Solution
Knowledge Check
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?
View SolutionA and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?
View SolutionU, V and W together can complete a work in 10 days. If U alone can complete the work in 20 days and V alone can complete the work in 30 days, then in how many days W alone can complete the work?
View SolutionC alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?
View SolutionX, Y and Z together can complete a work in 20 days. Y and Z can complete the same work in 30 days. In how many days X alone can complete the same work?
View Solution