A can do a work in 20 days. B can do a work in 30 days and C can do a work in 60 days. If 'B' and 'C' helps A every third day, then how many days after work will complete?
12 days
15 days
18 days
10 days
The correct Answer is:B
To solve the problem step by step, we will calculate the work done by A, B, and C over a cycle of 3 days, where B and C help A every third day.
Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 30 days, so B's work rate is:
Work rate of B=130 (work per day)
- C can complete the work in 60 days, so C's work rate is:
Work rate of C=160 (work per day)
Step 2: Calculate the work done in 2 days by A.
In the first two days, only A is working:
- Work done by A in 2 days:
Work done by A in 2 days=2×120=220=110
Step 3: Calculate the work done on the 3rd day by A, B, and C together.
On the 3rd day, A, B, and C work together:
- Total work done by A, B, and C in 1 day:
Total work=120+130+160
To add these fractions, we need a common denominator, which is 60:
120=360,130=260,160=160
So,
Total work=360+260+160=660=110
Step 4: Calculate the total work done in 3 days.
- Work done in 3 days (2 days by A + 1 day by A, B, and C):
Total work in 3 days=110+110=210=15
Step 5: Determine how many cycles are needed to complete the work.
Since 15 of the work is completed in 3 days, we need to find out how many such cycles are required to complete the entire work (1 work):
Number of cycles required=115=5
Step 6: Calculate the total number of days to complete the work.
- Total days to complete the work:
Total days=5 cycles×3 days per cycle=15 days
Final Answer:
The work will be completed in 15 days.
---
- A can complete the work in 20 days, so A's work rate is:
Work rate of A=120 (work per day)
- B can complete the work in 30 days, so B's work rate is:
Work rate of B=130 (work per day)
- C can complete the work in 60 days, so C's work rate is:
Work rate of C=160 (work per day)
In the first two days, only A is working:
- Work done by A in 2 days:
Work done by A in 2 days=2×120=220=110
On the 3rd day, A, B, and C work together:
- Total work done by A, B, and C in 1 day:
Total work=120+130+160
To add these fractions, we need a common denominator, which is 60:
120=360,130=260,160=160
So,
Total work=360+260+160=660=110
- Work done in 3 days (2 days by A + 1 day by A, B, and C):
Total work in 3 days=110+110=210=15
Since 15 of the work is completed in 3 days, we need to find out how many such cycles are required to complete the entire work (1 work):
Number of cycles required=115=5
Step 6: Calculate the total number of days to complete the work.
- Total days to complete the work:
Total days=5 cycles×3 days per cycle=15 days
The work will be completed in 15 days.
Topper's Solved these Questions
Similar Questions
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA and C can do a work in 12 days while A,B and C can do the work in 4 days. In how many days can B do the work alone?
View Solution
Knowledge Check
A can do a work in 20 days. B can do a work in 30 days and C can do a work in 60 days. If 'B' and 'C' helps A every third day, then how many days after work will complete?
A12 daysB15 daysC18 daysD10 daysA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
A24 daysB18 daysC20 daysD16 daysA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
A15B16C10D12
A can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionA can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?
View SolutionA can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
View SolutionA and B can do a work in 12 days, B and C can do the same work in 15 days & C and A can do it in 20 days. In how many days they can do it separately?
View SolutionA and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
View Solution