15 persons can complete a work in 60 days. If the number of persons is increased by 5, how many days earlier will the work get completed ?
5 days
10 days
15 days
45 days
The correct Answer is:C
To solve the problem, we need to determine how many days earlier the work will be completed when the number of workers is increased from 15 to 20. Here’s a step-by-step solution:
Step 1: Calculate the total work in person-days
First, we calculate the total amount of work done in person-days. If 15 persons can complete the work in 60 days, the total work can be calculated as:
Total Work=Number of Persons×Number of Days=15×60=900 person-days
Hint: To find the total work, multiply the number of workers by the number of days they work.
Step 2: Determine the new number of workers
Next, we increase the number of workers by 5. Therefore, the new number of workers is:
New Number of Persons=15+5=20
Hint: When the number of workers increases, simply add the increase to the original number of workers.
Step 3: Calculate the number of days required with the new number of workers
Now, we need to find out how many days it will take for 20 persons to complete the same amount of work (900 person-days). We can set up the equation:
Number of Days=Total WorkNumber of Persons=90020
Calculating this gives:
Number of Days=45 days
Hint: To find the number of days required, divide the total work by the new number of workers.
Step 4: Calculate how many days earlier the work gets completed
Now, we find out how many days earlier the work is completed by subtracting the new number of days from the original number of days:
Days Earlier=Original Days−New Days=60−45=15 days
Hint: To find out how much earlier the work is completed, subtract the new completion time from the original completion time.
Final Answer
The work will be completed 15 days earlier.
First, we calculate the total amount of work done in person-days. If 15 persons can complete the work in 60 days, the total work can be calculated as:
Total Work=Number of Persons×Number of Days=15×60=900 person-days
Next, we increase the number of workers by 5. Therefore, the new number of workers is:
New Number of Persons=15+5=20
Now, we need to find out how many days it will take for 20 persons to complete the same amount of work (900 person-days). We can set up the equation:
Number of Days=Total WorkNumber of Persons=90020
Calculating this gives:
Number of Days=45 days
Now, we find out how many days earlier the work is completed by subtracting the new number of days from the original number of days:
Days Earlier=Original Days−New Days=60−45=15 days
The work will be completed 15 days earlier.
Similar Questions
Certain number of persons can complete a work in100 days. If 10 persons were less, it would have taken10 days more for the work to be completed. Number of persons in the beginning is :
View Solution30 persons can complete a work in 10 days. If they work 4 hours per day, then in how many days 45 persons can complete double the work if they work 8 hours per day? It is known that 2 persons of first type can do the same work in 2 hours that can be completed by 4 persons of 2nd type in 1 hour.
View Solution
Knowledge Check
A certain number of persons can complete a work in 34 days working 9 hours a day. If the number of persons is decreased by 40%, then how many hours a day should the remaining persons work to complete the work in 51 days ?
कुछ व्यक्ति किसी कार्य को एक दिन में 9 घंटे कार्य करते हुए 34 दिनों में पूरा कर सकते हैं | यदि व्यक्तियों की संख्या 40% से कम कर दी जाए, तो शेष व्यक्तियों को इस कार्य को 51 दिनों में पूरा करने के लिए दिन में कितने घंटे कार्य करना पड़ेगा ?A9B8C12D1010 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?
A6B613C623D72325 persons can complete a work in 60 days. They started the work. 10 people left the work after x days. If the whole work was completed in 80 days, then what is the value of x ?
25 व्यक्ति किसी कार्य को 60 दिनों में पूरा कर सकते हैं | उन्होंने कार्य शुरू किया | x दिनों के बाद 10 लोगों ने कार्य छोड़ दिया | यदि पूरा कार्य 80 दिनों में पूरा हुआ, तो x का मान ज्ञात करें |A9B8C12D30
25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?
View SolutionA and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View SolutionIf 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
View Solution