A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days B could finish the work?
A और B मिलकर एक काम 12 दिन में कर सकते हैं जसे B और C मिलकर 16 दिन में कर सकते हैं। A द्वारा उस पर 5 दिन और B द्वारा 7 दिन करने के बाद C ने उसे 13 दिन में पूरा कर दिया। B उस काम को कितने दिन में पूरा कर सकता था? Options are (a) 48 day/ 48 दिन (b)24 day/ 24 दिन (c)16 day/ 16 दिन (d)12 day/ 12 दिन
48 day/ 48 दिन
24 day/ 24 दिन
16 day/ 16 दिन
12 day/ 12 दिन
The correct Answer is:A
To solve the problem, we need to find out how many days B can finish the work alone. Let's break it down step by step.
Step 1: Determine the work rates of A, B, and C
1. A and B's work rate: A and B together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A + B=112 (work per day)
2. B and C's work rate: B and C together can complete the work in 16 days. Therefore, their combined work rate is:
Work rate of B + C=116 (work per day)
Step 2: Set up equations for individual work rates
Let:
- A's work rate = a
- B's work rate = b
- C's work rate = c
From the above information, we can write the following equations:
1. a+b=112 (1)
2. b+c=116 (2)
Step 3: Work done by A, B, and C
Now, we know:
- A works for 5 days, so the work done by A is:
Work done by A=5a
- B works for 7 days, so the work done by B is:
Work done by B=7b
- C finishes the remaining work in 13 days, so the work done by C is:
Work done by C=13c
Step 4: Total work equation
The total work done by A, B, and C together should equal 1 (the whole work):
5a+7b+13c=1(3)
Step 5: Substitute for c
From equation (2), we can express c in terms of b:
c=116−b
Step 6: Substitute c into equation (3)
Substituting c into equation (3):
5a+7b+13(116−b)=1
Expanding this gives:
5a+7b+1316−13b=1
Combining like terms:
5a−6b+1316=1
Rearranging gives:
5a−6b=1−1316=316(4)
Step 7: Solve the system of equations
Now we have two equations:
1. a+b=112 (1)
2. 5a−6b=316 (4)
From equation (1), we can express a:
a=112−b
Substituting this into equation (4):
5(112−b)−6b=316
Expanding gives:
512−5b−6b=316
Combining terms:
512−11b=316
Now, convert 512 to a fraction with a denominator of 48:
512=2048,316=948
So, we have:
2048−11b=948
Rearranging gives:
11b=2048−948=1148
Thus:
b=1148×11=148
Step 8: Calculate the days B can finish the work
Since b is the work rate of B, the number of days B can finish the work alone is:
Days for B=1b=48 days
Final Answer
B can finish the work in 48 days.
Work rate of A + B=112 (work per day)
Work rate of B + C=116 (work per day)
- A's work rate = a
- B's work rate = b
- C's work rate = c
1. a+b=112 (1)
2. b+c=116 (2)
- A works for 5 days, so the work done by A is:
Work done by A=5a
Work done by B=7b
Work done by C=13c
5a+7b+13c=1(3)
c=116−b
5a+7b+13(116−b)=1
Expanding this gives:
5a+7b+1316−13b=1
Combining like terms:
5a−6b+1316=1
Rearranging gives:
5a−6b=1−1316=316(4)
1. a+b=112 (1)
2. 5a−6b=316 (4)
a=112−b
Substituting this into equation (4):
5(112−b)−6b=316
Expanding gives:
512−5b−6b=316
Combining terms:
512−11b=316
Now, convert 512 to a fraction with a denominator of 48:
512=2048,316=948
So, we have:
2048−11b=948
Rearranging gives:
11b=2048−948=1148
Thus:
b=1148×11=148
Days for B=1b=48 days
B can finish the work in 48 days.
Similar Questions
A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionA and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View Solution
Knowledge Check
A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48 daysB24 daysC16 daysD12 daysA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
A20 daysB25 daysC15 daysD18 daysA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
A15 daysB18 daysC20 daysD25 days
A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View SolutionA and B together can do a piece of work in 12 days, While B alone can finish it in 30 days. A alone can finish the work in how many days?
View SolutionA and B together can be do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work in how many days /
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View Solution