A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days B could finish the work?
A और B मिलकर एक काम 12 दिन में कर सकते हैं जसे B और C मिलकर 16 दिन में कर सकते हैं। A द्वारा उस पर 5 दिन और B द्वारा 7 दिन करने के बाद C ने उसे 13 दिन में पूरा कर दिया। B उस काम को कितने दिन में पूरा कर सकता था? Options are (a) 48 day/ 48 दिन (b)24 day/ 24 दिन (c)16 day/ 16 दिन (d)12 day/ 12 दिन

A

48 day/ 48 दिन

B

24 day/ 24 दिन

C

16 day/ 16 दिन

D

12 day/ 12 दिन

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to find out how many days B can finish the work alone. Let's break it down step by step.

Step 1: Determine the work rates of A, B, and C

1. A and B's work rate: A and B together can complete the work in 12 days. Therefore, their combined work rate is:
Work rate of A + B=112 (work per day)

2. B and C's work rate: B and C together can complete the work in 16 days. Therefore, their combined work rate is:
Work rate of B + C=116 (work per day)

Step 2: Set up equations for individual work rates

Let:
- A's work rate = a
- B's work rate = b
- C's work rate = c

From the above information, we can write the following equations:
1. a+b=112 (1)
2. b+c=116 (2)

Step 3: Work done by A, B, and C

Now, we know:
- A works for 5 days, so the work done by A is:
Work done by A=5a

- B works for 7 days, so the work done by B is:
Work done by B=7b

- C finishes the remaining work in 13 days, so the work done by C is:
Work done by C=13c

Step 4: Total work equation

The total work done by A, B, and C together should equal 1 (the whole work):
5a+7b+13c=1(3)

Step 5: Substitute for c

From equation (2), we can express c in terms of b:
c=116b

Step 6: Substitute c into equation (3)

Substituting c into equation (3):
5a+7b+13(116b)=1
Expanding this gives:
5a+7b+131613b=1
Combining like terms:
5a6b+1316=1
Rearranging gives:
5a6b=11316=316(4)

Step 7: Solve the system of equations

Now we have two equations:
1. a+b=112 (1)
2. 5a6b=316 (4)

From equation (1), we can express a:
a=112b
Substituting this into equation (4):
5(112b)6b=316
Expanding gives:
5125b6b=316
Combining terms:
51211b=316
Now, convert 512 to a fraction with a denominator of 48:
512=2048,316=948
So, we have:
204811b=948
Rearranging gives:
11b=2048948=1148
Thus:
b=1148×11=148

Step 8: Calculate the days B can finish the work

Since b is the work rate of B, the number of days B can finish the work alone is:
Days for B=1b=48 days

Final Answer
B can finish the work in 48 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48 days
    B24 days
    C16 days
    D12 days
  • A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A20 days
    B25 days
    C15 days
    D18 days
  • A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A15 days
    B18 days
    C20 days
    D25 days