A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?

A

17.5

B

10

C

15

D

12

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will analyze the work done by A and B, calculate their individual work rates, and determine how long it takes to complete the entire task.

Step 1: Determine the work rates of A and B
- A can finish 80% of the task in 12 days.
- Therefore, A can complete 100% of the task in:
Total days for A=12 days0.8=15 days
- B can finish 20% of the task in 2 days.
- Therefore, B can complete 100% of the task in:
Total days for B=2 days0.2=10 days

Step 2: Calculate the work done by A and B in one day
- A's work rate:
Work rate of A=115 of the task per day
- B's work rate:
Work rate of B=110 of the task per day

Step 3: Calculate the work done together in 2 days
- In 2 days, A and B together will complete:
Work done by A in 2 days=2×115=215
Work done by B in 2 days=2×110=210=15
- Total work done in 2 days:
Total work done=215+15=215+315=515=13

Step 4: Calculate the remaining work
- Total work is 1 (100% of the task), so the remaining work after 2 days is:
Remaining work=113=23

Step 5: Calculate how long A takes to finish the remaining work
- Since A can complete the entire task in 15 days, the time taken by A to complete 23 of the task is:
Time for A to complete remaining work=23×15=10 days

Step 6: Calculate the total time taken for the entire task
- Total time taken = Time worked together (2 days) + Time taken by A to finish remaining work (10 days):
Total time=2+10=12 days

Thus, the entire task was completed in 12 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
    A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?

    A10
    B12
    C9
    D15
  • A can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
    A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?

    A16
    B8
    C21
    D11
  • A can finish 35 of a task in 6 days and B can finish 23 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:

    A10 days
    B18 days
    C12 days
    D15 days