A can finish 25 of a task in 12 days and B can finish 23 of the same task in 30 days. They work together for 10 days. C alone completes the remaining task in 16 days. B and C together will complete 45 of the same task in:
16 days
12 days
20 days
15 days
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by A, B, and C individually, then find out how much work they do together, and finally calculate how long it will take for B and C to complete 45 of the task.
Step 1: Calculate A's one-day work
A can finish 25 of the task in 12 days.
A's one-day work=25÷12=25×112=260=130
Step 2: Calculate B's one-day work
B can finish 23 of the task in 30 days.
B's one-day work=23÷30=23×130=290=145
Step 3: Calculate the combined one-day work of A and B
Now, we add A's and B's one-day work:
A's one-day work+B's one-day work=130+145
To add these fractions, we need a common denominator, which is 90:
130=390,145=290
Combined work of A and B=390+290=590=118
Step 4: Calculate the work done by A and B in 10 days
In 10 days, A and B together will complete:
Work done in 10 days=10×118=1018=59
Step 5: Calculate the remaining work
The total work is considered as 1 (the whole task). Therefore, the remaining work after A and B work for 10 days is:
Remaining work=1−59=49
Step 6: Calculate C's one-day work
C can complete the remaining 49 of the task in 16 days. Thus, C's one-day work is:
C's one-day work=49÷16=49×116=4144=136
Step 7: Calculate the combined one-day work of B and C
Now, we find the combined work of B and C:
B's one-day work+C's one-day work=145+136
The common denominator for 45 and 36 is 180:
145=4180,136=5180
Combined work of B and C=4180+5180=9180=120
Step 8: Calculate the time taken by B and C to complete 45 of the task
To find out how long it will take for B and C to complete 45 of the task:
Time=Work÷Rate=45÷120
This is equivalent to:
Time=45×20=16 days
Final Answer
B and C together will complete 45 of the task in 16 days.
---
A can finish 25 of the task in 12 days.
B can finish 23 of the task in 30 days.
Now, we add A's and B's one-day work:
Combined work of A and B=390+290=590=118
In 10 days, A and B together will complete:
The total work is considered as 1 (the whole task). Therefore, the remaining work after A and B work for 10 days is:
C can complete the remaining 49 of the task in 16 days. Thus, C's one-day work is:
Now, we find the combined work of B and C:
Combined work of B and C=4180+5180=9180=120
To find out how long it will take for B and C to complete 45 of the task:
B and C together will complete 45 of the task in 16 days.
Topper's Solved these Questions
- SSC PREVIOUS YEAR PAPER HSC LEVEL (15 OCT 2019)BOOK - SSC SELECTION POSTCHAPTER - SSC PREVIOUS YEAR PAPER HSC LEVEL (15 OCT 2019)EXERCISE - Section : Quantitative Aptitude Basic Arithmetic Skill
25 Videos
- SSC PREVIOUS YEAR PAPER MATRIC LEVEL (14 OCT 2019 SHIFT 1)BOOK - SSC SELECTION POSTCHAPTER - SSC PREVIOUS YEAR PAPER MATRIC LEVEL (14 OCT 2019 SHIFT 1)EXERCISE - SECTION : QUANTITATIVE APTITUDE BASIC ARITHMETIC SKILL
25 Videos
Similar Questions
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
View SolutionA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
View Solution
Knowledge Check
A can finish 25 of a task in 12 days and B can finish 23 of the same task in 30 days .They work together for 10 days .C alone completes the remaining task remaining task in 16 days .B and C together will complete 45 of the same task in :
A16 daysB12 daysC20 daysD15 daysA can finish 35 of a task in 6 days and B can finish 23 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:
A10 daysB18 daysC12 daysD15 daysA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
A8 daysB5 daysC4 daysD6 days
A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
View SolutionA can finish a task in 45 days and B can finish the same task in 30 days. They work together for 3 days and then A leaves. In how many days will B finish the remaining task?
View SolutionA can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View SolutionX can complete a task in 8 days, whereas Y can complete the same task in 10 days. If they work together, in how many days will the task be completed?
View Solution