A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?

A

10

B

13.75

C

12.5

D

11.25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we need to determine how many days A and B worked together before A left 12.5 days before the work was completed.

Step 1: Determine the work done by A and B together.
A and B can complete the task together in 15 days. Therefore, the work done by A and B in one day is:
Work rate of A and B together=115 of the work per day

Step 2: Determine the work done by A alone.
A can complete the task alone in 18.75 days. Therefore, the work done by A in one day is:
Work rate of A=118.75=475 of the work per day

Step 3: Determine the work done by B alone.
Let the work done by B in one day be b. Since A and B together can complete the work in 15 days, we have:
115=475+b
To find b, we first convert 115 to a fraction with a common denominator:
115=575
Now substituting:
575=475+b
Subtracting 475 from both sides gives:
b=575475=175 of the work per day

Step 4: Determine the total work.
The total work can be considered as 1 unit of work.

Step 5: Determine how much work is left when A leaves.
A leaves 12.5 days before the work is completed. Let x be the total number of days they worked together. Therefore, the total time to complete the work is x+12.5 days. The work done in the last 12.5 days by B alone is:
Work done by B in 12.5 days=12.5×175=12.575=16 of the work

Step 6: Calculate the work done together.
If B completed 16 of the work alone, then the work done together by A and B is:
Work done together=116=56 of the work

Step 7: Calculate the number of days they worked together.
Since A and B together can complete 115 of the work per day, we can find the number of days they worked together:
Days worked together=56115=56×15=756=12.5 days

Conclusion:
A and B worked together for 12.5 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

    A10
    B12
    C9
    D11
  • A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

    A6
    B5
    C7
    D7.2
  • F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

    A1305 days
    B1067 days
    C1147 days
    D1207 days