Doubtnut Promotions Sticky

A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?

A

10

B

13.75

C

12.5

D

11.25

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Practice Problems

  • Question 1 - Select One

    A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

    A10
    B12
    C9
    D11
  • Question 1 - Select One

    A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

    A6
    B5
    C7
    D7.2
  • Question 1 - Select One

    F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

    A1305 days
    B1067 days
    C1147 days
    D1207 days
  • Question 1 - Select One

    P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

    A9 days
    B14 days
    C12 days
    D18 days
  • Question 1 - Select One

    A and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?

    A13 days
    B8 days
    C6 days
    D5 days
  • Question 1 - Select One

    A can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?

    A12 days
    B8 days
    C9 days
    D1012 days
  • Question 1 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • Question 1 - Select One

    K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?

    A352 days
    B252 days
    C552 days
    D452 days

Similar Questions