A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?
10
13.75
12.5
11.25
The correct Answer is:C
To solve the problem step by step, we need to determine how many days A and B worked together before A left 12.5 days before the work was completed.
Step 1: Determine the work done by A and B together.
A and B can complete the task together in 15 days. Therefore, the work done by A and B in one day is:
Work rate of A and B together=115 of the work per day
Step 2: Determine the work done by A alone.
A can complete the task alone in 18.75 days. Therefore, the work done by A in one day is:
Work rate of A=118.75=475 of the work per day
Step 3: Determine the work done by B alone.
Let the work done by B in one day be b. Since A and B together can complete the work in 15 days, we have:
115=475+b
To find b, we first convert 115 to a fraction with a common denominator:
115=575
Now substituting:
575=475+b
Subtracting 475 from both sides gives:
b=575−475=175 of the work per day
Step 4: Determine the total work.
The total work can be considered as 1 unit of work.
Step 5: Determine how much work is left when A leaves.
A leaves 12.5 days before the work is completed. Let x be the total number of days they worked together. Therefore, the total time to complete the work is x+12.5 days. The work done in the last 12.5 days by B alone is:
Work done by B in 12.5 days=12.5×175=12.575=16 of the work
Step 6: Calculate the work done together.
If B completed 16 of the work alone, then the work done together by A and B is:
Work done together=1−16=56 of the work
Step 7: Calculate the number of days they worked together.
Since A and B together can complete 115 of the work per day, we can find the number of days they worked together:
Days worked together=56115=56×15=756=12.5 days
Conclusion:
A and B worked together for 12.5 days.
A and B can complete the task together in 15 days. Therefore, the work done by A and B in one day is:
Work rate of A and B together=115 of the work per day
A can complete the task alone in 18.75 days. Therefore, the work done by A in one day is:
Work rate of A=118.75=475 of the work per day
Let the work done by B in one day be b. Since A and B together can complete the work in 15 days, we have:
115=475+b
To find b, we first convert 115 to a fraction with a common denominator:
115=575
Now substituting:
575=475+b
Subtracting 475 from both sides gives:
b=575−475=175 of the work per day
The total work can be considered as 1 unit of work.
A leaves 12.5 days before the work is completed. Let x be the total number of days they worked together. Therefore, the total time to complete the work is x+12.5 days. The work done in the last 12.5 days by B alone is:
Work done by B in 12.5 days=12.5×175=12.575=16 of the work
If B completed 16 of the work alone, then the work done together by A and B is:
Work done together=1−16=56 of the work
Since A and B together can complete 115 of the work per day, we can find the number of days they worked together:
Days worked together=56115=56×15=756=12.5 days
A and B worked together for 12.5 days.
Similar Questions
A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
A10B12C9D11A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?
A6B5C7D7.2F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?
A1305 daysB1067 daysC1147 daysD1207 days
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionK alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?
View Solution