A and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?
8 days
6 days
14 days
12 days
The correct Answer is:A
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A and B
- A can complete the task in 40 days, so A's work rate is:
Work rate of A=1 task40 days=140 tasks per day
- B can complete the task in 16 days, so B's work rate is:
Work rate of B=1 task16 days=116 tasks per day
Step 2: Calculate the total work in terms of units
- To find a common unit for the work, we can use the least common multiple (LCM) of 40 and 16. The LCM of 40 and 16 is 80. Therefore, we can consider the total work to be 80 units.
Step 3: Calculate the work done by A in the first 12 days
- In 12 days, A will complete:
Work done by A in 12 days=12×140=1240=310 of the task
- In terms of units, this is:
Units completed by A=12×2=24 units
Step 4: Calculate the remaining work after A's initial 12 days
- The total work is 80 units, and A has completed 24 units. Therefore, the remaining work is:
Remaining work=80−24=56 units
Step 5: Calculate the combined work rate of A and B
- When B joins A, their combined work rate is:
Combined work rate=140+116
- To add these fractions, we find a common denominator (which is 80):
140=280,116=580
- Therefore,
Combined work rate=280+580=780 tasks per day
Step 6: Calculate the time taken to complete the remaining work
- To find the time taken to complete the remaining 56 units of work at the combined rate of 780 tasks per day, we set up the equation:
Time=Remaining workCombined work rate=56780=56×807=44807≈640 days
Step 7: Final Calculation
- The exact time in days is:
Time=640÷7≈91.43 days
Conclusion
The task lasted approximately 91.43 days after B joined.
---
- A can complete the task in 40 days, so A's work rate is:
Work rate of A=1 task40 days=140 tasks per day
- B can complete the task in 16 days, so B's work rate is:
Work rate of B=1 task16 days=116 tasks per day
- To find a common unit for the work, we can use the least common multiple (LCM) of 40 and 16. The LCM of 40 and 16 is 80. Therefore, we can consider the total work to be 80 units.
- In 12 days, A will complete:
Work done by A in 12 days=12×140=1240=310 of the task
- In terms of units, this is:
Units completed by A=12×2=24 units
- The total work is 80 units, and A has completed 24 units. Therefore, the remaining work is:
Remaining work=80−24=56 units
- When B joins A, their combined work rate is:
Combined work rate=140+116
- To add these fractions, we find a common denominator (which is 80):
140=280,116=580
- Therefore,
Combined work rate=280+580=780 tasks per day
- To find the time taken to complete the remaining 56 units of work at the combined rate of 780 tasks per day, we set up the equation:
Time=Remaining workCombined work rate=56780=56×807=44807≈640 days
- The exact time in days is:
Time=640÷7≈91.43 days
The task lasted approximately 91.43 days after B joined.
Similar Questions
Smith and Ajit can complete a task in 12 days and 18 days respectively. If they work together on a task for 4 days, then the fraction of task that will be left is:
View SolutionTwo persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :
View Solution
Knowledge Check
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 daysA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 daysPruthi and Shakil can complete a work in 20 days and 12 days respectively. Pruthi alone started the work and Shakil joined him after 4 days till the completion of the work. How long dd the work last?
A5 daysB10 daysC14 daysD22 days
A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
View SolutionRavi can complete a task in 6 days and Mohan can complete the same task in 9 days. In how many days can Ravi and Mohan together complete the same task?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View SolutionA , B and C can finish a task in 42 days, 84 days and 28 days, respectively. A started the work. B joined him after 3 days. If C joined them after 5 days from the beginning, then for how many days did A work till the completion of the task?
A, B और C किसी कार्य को क्रमशः 42 दिन, 84 दिन और 28 दिन में कर सकते हैं | A ने कार्य शुरू किया तथा 8 3 दिन बाद उसमें शामिल हुआ | यदि C ने आरम्भ से 5 दिनों के बाद कार्य करना शुरू किया, तो A कार्य पूरा होने तक कितने दिनों तक कार्य करता रहा ?
View SolutionA and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?
View Solution