Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :

A

8

B

9

C

10

D

12

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days it takes for A and B to complete the task together, given that A leaves 5 days before the task is completed and B finishes the remaining work alone.

1. Determine the Work Rates of A and B:
- A can complete the task in 10 days, so A's work rate is:
Work rate of A=110 (tasks per day)
- B can complete the task in 15 days, so B's work rate is:
Work rate of B=115 (tasks per day)

2. Find the Least Common Multiple (LCM) to Determine Total Work:
- The LCM of 10 and 15 is 30. Therefore, we can consider the total work as 30 units.

3. Calculate the Daily Work Contribution:
- A's daily contribution:
A's daily work=3010=3 units/day
- B's daily contribution:
B's daily work=3015=2 units/day

4. Let the Total Time Taken to Complete the Task be X Days:
- A works for X5 days (since A leaves 5 days before the task is completed).
- B works for X days.

5. Set Up the Equation for Total Work Done:
- The total work done can be expressed as:
Work done by A+Work done by B=Total Work
- This translates to:
3(X5)+2X=30

6. Simplify the Equation:
- Expanding the equation:
3X15+2X=30
- Combining like terms:
5X15=30

7. Solve for X:
- Adding 15 to both sides:
5X=45
- Dividing by 5:
X=9

8. Conclusion:
- The total number of days taken to complete the whole task is 9 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10
  • Question 2 - Select One

    A and B can complete a work in 12 days and 15 days respectively. They started the work together. If after 4 days A leaves the job, then in how many days B will complete the remaining work?

    A2 days
    B3 days
    C4 days
    D112 days
  • Question 3 - Select One

    Smith and Ajit can complete a task in 12 days and 18 days respectively. If they work together on a task for 4 days, then the fraction of task that will be left is:

    A49
    B19
    C29
    D59