A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time?
The correct Answer is:20
Step by step video, text & image solution for A contractor wants to complete a project in 90 days and he employed 60 workmen. After 60 days 3/4 of the work is completed. Then how many persons should he remove so that the project will be completed in stipulated time? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.
Updated on:21/07/2023Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (a)
27 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (b)
15 Videos
- SURDS BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SURDS EXERCISE - UNIT TEST -1
15 Videos
- TRIANGLES BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLES EXERCISE - Self Assessment Sheet
10 Videos
Similar Questions
A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View Solution15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers
View Solution
Knowledge Check
A contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?A20 menB25 menC30 menD40 menA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
A495B514C528D532A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
A162B234C262D81
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View Solution