If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can complete the work in 2 days then in how many days the work will be completed by 15 men and 20 boys?

A

10 days

B

4 days

C

8 days

D

5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days it will take for 15 men and 20 boys to complete a piece of work, given the work rates of different groups.

1. Determine the Work Done by 6 Men and 8 Boys in 10 Days:
- Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.
- The total work done by 6 men and 8 boys in 10 days can be expressed as:
Total Work=(6M+8B)×10

2. Determine the Work Done by 26 Men and 48 Boys in 2 Days:
- Similarly, the total work done by 26 men and 48 boys in 2 days is:
Total Work=(26M+48B)×2

3. Set the Two Expressions for Total Work Equal:
- Since both expressions represent the same total work, we can set them equal to each other:
(6M+8B)×10=(26M+48B)×2

4. Simplify the Equation:
- Expanding both sides gives:
60M+80B=52M+96B
- Rearranging the equation yields:
60M52M=96B80B
8M=16B
- Dividing both sides by 8 gives:
M=2B

5. Calculate the Total Work in Units:
- Now, substituting M=2B back into the work equation:
Total Work=(6M+8B)×10=(6(2B)+8B)×10
=(12B+8B)×10=20B×10=200B
- Thus, the total work is 200 units.

6. Calculate the Efficiency of 15 Men and 20 Boys:
- The efficiency of 15 men and 20 boys can be calculated as:
Efficiency=15M+20B
- Substituting M=2B:
=15(2B)+20B=30B+20B=50B

7. Determine the Number of Days Required to Complete the Work:
- To find the number of days required to complete 200 units of work with an efficiency of 50B:
Days=Total WorkEfficiency=200B50B=4 days

Final Answer:
The work will be completed by 15 men and 20 boys in 4 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

    A2 days
    B4 days
    C6 days
    D16 days
  • 12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?

    A12
    B10
    C9
    D8
  • If 12 men and 16 boys can complete a piece of work in 5 days and 13 men and 24 boys can complete the same work in 4 days, then in how many days 7 men and 10 boys will complete this work?

    A8 days
    B9 days
    C813 days
    D1013 days