If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can complete the work in 2 days then in how many days the work will be completed by 15 men and 20 boys?
10 days
4 days
8 days
5 days
The correct Answer is:B
To solve the problem, we need to determine how many days it will take for 15 men and 20 boys to complete a piece of work, given the work rates of different groups.
1. Determine the Work Done by 6 Men and 8 Boys in 10 Days:
- Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.
- The total work done by 6 men and 8 boys in 10 days can be expressed as:
Total Work=(6M+8B)×10
2. Determine the Work Done by 26 Men and 48 Boys in 2 Days:
- Similarly, the total work done by 26 men and 48 boys in 2 days is:
Total Work=(26M+48B)×2
3. Set the Two Expressions for Total Work Equal:
- Since both expressions represent the same total work, we can set them equal to each other:
(6M+8B)×10=(26M+48B)×2
4. Simplify the Equation:
- Expanding both sides gives:
60M+80B=52M+96B
- Rearranging the equation yields:
60M−52M=96B−80B
8M=16B
- Dividing both sides by 8 gives:
M=2B
5. Calculate the Total Work in Units:
- Now, substituting M=2B back into the work equation:
Total Work=(6M+8B)×10=(6(2B)+8B)×10
=(12B+8B)×10=20B×10=200B
- Thus, the total work is 200 units.
6. Calculate the Efficiency of 15 Men and 20 Boys:
- The efficiency of 15 men and 20 boys can be calculated as:
Efficiency=15M+20B
- Substituting M=2B:
=15(2B)+20B=30B+20B=50B
7. Determine the Number of Days Required to Complete the Work:
- To find the number of days required to complete 200 units of work with an efficiency of 50B:
Days=Total WorkEfficiency=200B50B=4 days
Final Answer:
The work will be completed by 15 men and 20 boys in 4 days.
---
- Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.
- The total work done by 6 men and 8 boys in 10 days can be expressed as:
Total Work=(6M+8B)×10
- Similarly, the total work done by 26 men and 48 boys in 2 days is:
Total Work=(26M+48B)×2
- Since both expressions represent the same total work, we can set them equal to each other:
(6M+8B)×10=(26M+48B)×2
- Expanding both sides gives:
60M+80B=52M+96B
- Rearranging the equation yields:
60M−52M=96B−80B
8M=16B
- Dividing both sides by 8 gives:
M=2B
- Now, substituting M=2B back into the work equation:
Total Work=(6M+8B)×10=(6(2B)+8B)×10
=(12B+8B)×10=20B×10=200B
- Thus, the total work is 200 units.
- The efficiency of 15 men and 20 boys can be calculated as:
Efficiency=15M+20B
- Substituting M=2B:
=15(2B)+20B=30B+20B=50B
- To find the number of days required to complete 200 units of work with an efficiency of 50B:
Days=Total WorkEfficiency=200B50B=4 days
The work will be completed by 15 men and 20 boys in 4 days.
Topper's Solved these Questions
Similar Questions
2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work?
View SolutionIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :
View Solution
Knowledge Check
If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in
A2 daysB4 daysC6 daysD16 days12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?
A12B10C9D8If 12 men and 16 boys can complete a piece of work in 5 days and 13 men and 24 boys can complete the same work in 4 days, then in how many days 7 men and 10 boys will complete this work?
A8 daysB9 daysC813 daysD1013 days
If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same work in 6 days, how long will 6 men and 24 boys take to complete the same work?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View SolutionIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :
View SolutionIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
A)6 days
B)4 days
C)8 days
D)7 days
View Solution2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?
View Solution