If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same work in 6 days, how long will 6 men and 24 boys take to complete the same work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first convert the work done by men and boys into a common unit and then find out how long 6 men and 24 boys will take to complete the work.

Step 1: Understand the work done by 9 men and 12 boys in 4 days
- Let the work done by 1 man in 1 day be M and the work done by 1 boy in 1 day be B.
- The total work done by 9 men and 12 boys in 4 days can be expressed as:
Total Work=(9M+12B)×4

Step 2: Understand the work done by 4 men and 16 boys in 6 days
- Similarly, the total work done by 4 men and 16 boys in 6 days can be expressed as:
Total Work=(4M+16B)×6

Step 3: Set the equations equal to each other
Since both expressions represent the same total work, we can set them equal:
(9M+12B)×4=(4M+16B)×6

Step 4: Simplify the equation
Expanding both sides gives:
36M+48B=24M+96B
Now, rearranging the equation:
36M24M=96B48B
12M=48B
Dividing both sides by 12:
M=4B
This means 1 man is equivalent to the work done by 4 boys.

Step 5: Convert the work done by 6 men and 24 boys into boys' work
Now we need to find out how much work 6 men and 24 boys can do:
- Work done by 6 men:
6M=6×4B=24B
- Total work done by 6 men and 24 boys:
6M+24B=24B+24B=48B

Step 6: Determine how long it will take for 6 men and 24 boys to complete the work
From our previous calculations, we know that 48 boys can complete the work in 4 days (from the first equation). Therefore, 6 men and 24 boys will also take:
Time=4 days

Final Answer
Thus, 6 men and 24 boys will take 4 days to complete the same work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

    A2 days
    B4 days
    C6 days
    D16 days
  • 2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .

    A50 days
    B60 days
    C30 days
    D55 days
  • If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
    A)6 days
    B)4 days
    C)8 days
    D)7 days

    A6 days
    B4 days
    C8 days
    D7 days