12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?
The correct Answer is: days.
To solve the problem, we need to determine how long it will take for 7 men and 10 boys to complete the same piece of work given the efficiencies of men and boys based on the information provided.
1. Define Variables:
Let the efficiency of one man be m and the efficiency of one boy be b.
2. Set Up Equations from Given Information:
From the first scenario:
- 12 men and 16 boys can complete the work in 5 days.
- The total work done can be expressed as:
Total Work=Efficiency×Time=(12m+16b)×5
Thus, we have:
60m+80b=W(1)
From the second scenario:
- 13 men and 24 boys can complete the work in 4 days.
- The total work done can be expressed as:
Total Work=(13m+24b)×4
Thus, we have:
52m+96b=W(2)
3. Equate the Two Expressions for Total Work:
Since both expressions equal the total work W, we can set them equal to each other:
60m+80b=52m+96b
4. Simplify the Equation:
Rearranging gives:
60m−52m=96b−80b
8m=16b
Dividing both sides by 8 gives:
m=2b(3)
5. Substitute m in One of the Work Equations:
We can substitute m from equation (3) into equation (1):
60(2b)+80b=W
120b+80b=W
200b=W
Thus, the total work W is 200b.
6. Find the Efficiency of 7 Men and 10 Boys:
Now, we calculate the efficiency of 7 men and 10 boys:
Efficiency=7m+10b
Substituting m=2b:
=7(2b)+10b=14b+10b=24b
7. Calculate the Time Taken by 7 Men and 10 Boys:
The time taken to complete the work is given by:
Time=Total WorkEfficiency=200b24b
The b cancels out:
=20024=253 days
Converting this to a mixed number:
=813 days
Final Answer:
Therefore, the time required for 7 men and 10 boys to complete the work is 813 days.
Let the efficiency of one man be m and the efficiency of one boy be b.
From the first scenario:
- 12 men and 16 boys can complete the work in 5 days.
- The total work done can be expressed as:
Total Work=Efficiency×Time=(12m+16b)×5
Thus, we have:
60m+80b=W(1)
- 13 men and 24 boys can complete the work in 4 days.
- The total work done can be expressed as:
Total Work=(13m+24b)×4
Thus, we have:
52m+96b=W(2)
Since both expressions equal the total work W, we can set them equal to each other:
60m+80b=52m+96b
Rearranging gives:
60m−52m=96b−80b
8m=16b
Dividing both sides by 8 gives:
m=2b(3)
We can substitute m from equation (3) into equation (1):
60(2b)+80b=W
120b+80b=W
200b=W
Thus, the total work W is 200b.
Now, we calculate the efficiency of 7 men and 10 boys:
Efficiency=7m+10b
Substituting m=2b:
=7(2b)+10b=14b+10b=24b
The time taken to complete the work is given by:
Time=Total WorkEfficiency=200b24b
The b cancels out:
=20024=253 days
Converting this to a mixed number:
=813 days
Therefore, the time required for 7 men and 10 boys to complete the work is 813 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Foundation Level)
51 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the same work in 6 days, how long will 6 men and 24 boys take to complete the same work?
View SolutionIf 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the
same work in 6 days, how long will 6 men and 24 boys take to complete the same work?
View Solution
Knowledge Check
If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in
A2 daysB4 daysC6 daysD16 days2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?
A1212 daysB1112 daysC1512 daysD1312 daysIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be
A)6 days
B)4 days
C)8 days
D)7 daysA6 daysB4 daysC8 daysD7 days
While 4 men and 6 boys can do a piece of work in 2 days, 1 man, and 3 boys can do the same work in 6 days. In how many days can 1 man and 1 boy complete the same work?
View Solution2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the work?
View SolutionIf 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :
View Solution2 men and 7 boys can do a piece of work in 4 days . 4 men and 4 boys can do the same work in 3 days . Then the number of days a boys a boy take to complete the same job is .
View SolutionIf 12 men and 16 boys can complete a piece of work in 5 days and 13 men and 24 boys can complete the same work in 4 days, then in how many days 7 men and 10 boys will complete this work?
View Solution