16 children can complete the work in 12 days, whereas 6 adults take 16 days to complete the same work. This work is started by 16 adults and after 3 days. 10 adults left the work, then, 4 children joined the work Accordingly, in how many days the remaining work get complete?

A

12 days

B

15 days

C

6 days

D

9 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the total work in terms of units
We know that 16 children can complete the work in 12 days.

- The total work done by 16 children in 12 days can be calculated as:
Total Work=Number of Children×Days=16×12=192 units

Step 2: Calculate the work done by 6 adults in 16 days
We also know that 6 adults can complete the same work in 16 days.

- The total work done by 6 adults in 16 days is also:
Total Work=6×16=96 units

Since both calculations represent the same total work, we can set them equal to each other to find the efficiency ratio between children and adults.

Step 3: Find the efficiency ratio of children and adults
From the previous calculations, we can find the efficiency of one adult in terms of children.

- Since 16 children do 192 units of work, the work done by 1 child in 1 day is:
Work per Child per Day=19216×12=1 unit

- For adults, since 6 adults do 192 units in 16 days, the work done by 1 adult in 1 day is:
Work per Adult per Day=1926×16=2 units

Thus, the ratio of efficiency of children to adults is:
Efficiency Ratio=1 (child):2 (adult)2:1

Step 4: Work done by 16 adults in 3 days
Now, we need to calculate how much work is done by 16 adults in the first 3 days.

- Since 1 adult does 2 units of work per day, 16 adults will do:
Work done by 16 adults in 1 day=16×2=32 units

- Therefore, in 3 days, the work done is:
Total Work in 3 Days=32×3=96 units

Step 5: Calculate the remaining work
Now, we subtract the work done in the first 3 days from the total work to find the remaining work.

- Remaining work:
Remaining Work=19296=96 units

Step 6: Work done after 3 days
After 3 days, 10 adults leave, leaving 6 adults. Then, 4 children join.

- Now we have 6 adults and 4 children working together. The work done by them in one day is:
Work done by 6 adults=6×2=12 units
Work done by 4 children=4×1=4 units

- Total work done by 6 adults and 4 children in one day:
Total Work in 1 Day=12+4=16 units

Step 7: Calculate the number of days to complete the remaining work
Now we need to find out how many days it will take to complete the remaining 96 units of work.

- Number of days required:
Days=Remaining WorkWork done in 1 Day=9616=6 days

Final Answer
Thus, the remaining work will be completed in 6 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?

    A18
    B12
    C24
    DCannot be determined
  • Question 2 - Select One

    12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

    A60 days
    B45 days
    C54 days
    D48 days
  • Question 3 - Select One

    A' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?

    A6
    B8
    C5
    D4