25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
36 days
88 days
94 days
None of these
The correct Answer is:A
To solve the problem step by step, let's break it down:
Step 1: Calculate the total work done by 25 men and 15 women in 12 days.
- Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
- The total work done by 25 men and 15 women in 12 days can be expressed as:
(25M+15W)×12=Total Work
Step 2: Calculate the total work done in terms of efficiency.
- We can simplify the equation:
25M+15W=Total Work12
Step 3: Work done in 8 days by 25 men and 15 women.
- In 8 days, the work done is:
(25M+15W)×8
Step 4: Calculate the remaining work after 8 days.
- The remaining work after 8 days is:
Remaining Work=Total Work−(25M+15W)×8
Step 5: Work done by 25 men in the next 6 days.
- The remaining work is completed by 25 men in 6 days:
25M×6=Remaining Work
Step 6: Set up the equation for total work.
- From the above steps, we can equate the remaining work:
(25M+15W)×12−(25M+15W)×8=25M×6
- Simplifying gives:
(25M+15W)×4=25M×6
Step 7: Solve for the ratio of men's and women's work.
- Rearranging gives:
25M+15W=25M×64
- This simplifies to:
25M+15W=37.5M
- Therefore:
15W=12.5M⟹MW=1512.5=65
Step 8: Calculate the total work in terms of women’s work.
- Let’s denote the total work as T:
T=25M×12+15W×12
- Substitute M=56W:
T=25(56W)×12+15W×12
T=1256W×12+15W×12
T=250W+180W=430W
Step 9: Calculate the time taken by 15 women to complete the work.
- The work done by 15 women in 1 day is:
15W
- Therefore, the time taken by 15 women to complete the total work T is:
Time=T15W=430W15W=43015=28.67 days
Conclusion
- The time required for 15 women to complete the work is approximately 28.67 days.
- Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
- The total work done by 25 men and 15 women in 12 days can be expressed as:
(25M+15W)×12=Total Work
- We can simplify the equation:
25M+15W=Total Work12
- In 8 days, the work done is:
(25M+15W)×8
- The remaining work after 8 days is:
Remaining Work=Total Work−(25M+15W)×8
- The remaining work is completed by 25 men in 6 days:
25M×6=Remaining Work
- From the above steps, we can equate the remaining work:
(25M+15W)×12−(25M+15W)×8=25M×6
- Simplifying gives:
(25M+15W)×4=25M×6
- Rearranging gives:
25M+15W=25M×64
- This simplifies to:
25M+15W=37.5M
- Therefore:
15W=12.5M⟹MW=1512.5=65
- Let’s denote the total work as T:
T=25M×12+15W×12
- Substitute M=56W:
T=25(56W)×12+15W×12
T=1256W×12+15W×12
T=250W+180W=430W
- The work done by 15 women in 1 day is:
15W
- Therefore, the time taken by 15 women to complete the total work T is:
Time=T15W=430W15W=43015=28.67 days
- The time required for 15 women to complete the work is approximately 28.67 days.
Topper's Solved these Questions
Similar Questions
15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .
View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 more men join the work.
View Solution
Knowledge Check
25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
A48 daysB24 daysC36 daysD60 days25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
A60 daysB88 daysC94 daysDNone of theseIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22
12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start’ working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to Complete the remaining work, if it is to be completed in 3 days?
View SolutionIf 3 men and 7 women can complete a work in 10 days and 4 men and 6 women need 8 days to complete the same work. In how many days will 10 women complete the same work?
View Solution12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution4 men and 6 women complete a work in 8 days. 2 men and 9 women also complete in 8 days in which. The number of days In which 18 women complete the work is :
View Solution