A contractor deployed some men to plant 1800 trees in a certain no. of days. But in 1/3rd of the planned time 120 plants could be less planted so to fulfill the target for the rest of the days everyday 20 more plants were planted. Thus it saved one day out of the initially planned no. of days. How many plants he planned to plant each day initially?
A)180
B)100
C)120
D)160
The correct Answer is:B
To solve the problem step by step, we will break down the information given and use it to find out how many plants the contractor initially planned to plant each day.
Step 1: Define Variables
Let x be the number of trees the contractor planned to plant each day initially. Let d be the total number of days planned to plant 1800 trees.
Step 2: Calculate Total Trees Planned
The total number of trees to be planted is 1800. Therefore, the equation for the total trees planted in d days is:
x⋅d=1800
Step 3: Determine Trees Planted in One-Third of Planned Time
In one-third of the planned time, the contractor would have worked for d3 days. The number of trees that should have been planted in this time is:
Trees planted=x⋅d3
However, it is given that 120 trees less were planted, so the actual number of trees planted is:
x⋅d3−120
Step 4: Calculate Remaining Trees
The remaining trees to be planted after one-third of the time is:
1800−(x⋅d3−120)=1800−x⋅d3+120
This simplifies to:
1800+120−x⋅d3=1920−x⋅d3
Step 5: Determine Remaining Days
The remaining time after one-third of the planned time is 2d3 days. However, since the contractor saves one day, the effective remaining days are:
2d3−1
Step 6: Calculate New Daily Planting Rate
To meet the target, the contractor plants 20 more trees each day than initially planned. Therefore, the new daily planting rate is:
x+20
The total trees planted in the remaining days is:
(x+20)(2d3−1)
Step 7: Set Up the Equation
Now we can set the equation for the remaining trees:
1920−x⋅d3=(x+20)(2d3−1)
Step 8: Expand and Simplify the Equation
Expanding the right side:
1920−x⋅d3=(x+20)⋅2d3−(x+20)
This gives:
1920−x⋅d3=2xd3+40d3−x−20
Step 9: Rearranging the Equation
Rearranging the equation to isolate x:
1920+20=2xd3+x+40d3+x⋅d3
This simplifies to:
1940=2xd+3xd+40d3
Step 10: Solve for x
To solve for x, we can substitute d from the first equation x⋅d=1800:
d=1800x
Substituting this back into the equation will allow us to solve for x.
Final Calculation
By solving the equations step by step, we can find the value of x which represents the number of trees the contractor planned to plant each day initially.
Let x be the number of trees the contractor planned to plant each day initially. Let d be the total number of days planned to plant 1800 trees.
The total number of trees to be planted is 1800. Therefore, the equation for the total trees planted in d days is:
x⋅d=1800
In one-third of the planned time, the contractor would have worked for d3 days. The number of trees that should have been planted in this time is:
Trees planted=x⋅d3
However, it is given that 120 trees less were planted, so the actual number of trees planted is:
x⋅d3−120
The remaining trees to be planted after one-third of the time is:
1800−(x⋅d3−120)=1800−x⋅d3+120
This simplifies to:
1800+120−x⋅d3=1920−x⋅d3
The remaining time after one-third of the planned time is 2d3 days. However, since the contractor saves one day, the effective remaining days are:
2d3−1
To meet the target, the contractor plants 20 more trees each day than initially planned. Therefore, the new daily planting rate is:
x+20
The total trees planted in the remaining days is:
(x+20)(2d3−1)
Now we can set the equation for the remaining trees:
1920−x⋅d3=(x+20)(2d3−1)
Expanding the right side:
1920−x⋅d3=(x+20)⋅2d3−(x+20)
This gives:
1920−x⋅d3=2xd3+40d3−x−20
Rearranging the equation to isolate x:
1920+20=2xd3+x+40d3+x⋅d3
This simplifies to:
1940=2xd+3xd+40d3
To solve for x, we can substitute d from the first equation x⋅d=1800:
d=1800x
Substituting this back into the equation will allow us to solve for x.
By solving the equations step by step, we can find the value of x which represents the number of trees the contractor planned to plant each day initially.
Topper's Solved these Questions
Similar Questions
Explain how the direction of exchange of gases in plants change with the time of the day.
View SolutionA contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time
View Solution
Knowledge Check
A contractor deployed some men to plant 1800 trees in a certain no. of days but in 13 rd of the planned time 120 plants could be planted so to full fill the target for the rest of the days every day 20 more plants were planted. Thus it saved on day out of the initially planned no. of days. How many plants he planned to plant each day initially?
Aa. 180Bb. 100Cc. 120Dd. 160A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?A24B20C18D15A certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially ?
A20B24C30D16
Explain how it is possible that a short day plant and a long day plant growing in the same location could flower on the same day of the year.
View SolutionA contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 15th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
View SolutionMr. Joshi has 430 cabbage - plants which he wants to plant out, some 25 to a row, the rest 20 to a row. If there are to be 18 rows in all, how many rows of 25 will there be ?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
View Solution