A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?
9
12
25
27
The correct Answer is:D
To solve the problem step by step, we will first determine the work rates of A and B, then calculate how much work they complete together in 3 days, and finally convert that into a percentage of the total work.
Step 1: Determine the work rates of A and B
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 work per day
- B can complete the work in 25 days. Therefore, B's work rate is:
Work rate of B=125 work per day
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=120+125
- To add these fractions, we need a common denominator. The least common multiple of 20 and 25 is 100.
120=5100,125=4100
Combined work rate=5100+4100=9100 work per day
Step 3: Calculate the total work done in 3 days
- In 3 days, the amount of work completed by A and B together is:
Work completed in 3 days=Combined work rate×3=9100×3=27100
Step 4: Convert the work done into a percentage of the total work
- To find the percentage of the total work completed, we multiply the fraction of work completed by 100:
Percentage of work completed=27100×100=27%
Final Answer
Thus, the percentage of the total work completed by A and B together in 3 days is 27%.
---
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 work per day
Work rate of B=125 work per day
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=120+125
120=5100,125=4100
Combined work rate=5100+4100=9100 work per day
- In 3 days, the amount of work completed by A and B together is:
Work completed in 3 days=Combined work rate×3=9100×3=27100
- To find the percentage of the total work completed, we multiply the fraction of work completed by 100:
Percentage of work completed=27100×100=27%
Thus, the percentage of the total work completed by A and B together in 3 days is 27%.
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionA can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.
View Solution
Knowledge Check
- Question 1 - Select One
Rahul can complete a work in 18 days and Sonu can complete the same work in 15 days. If both together work for 5 days, then what part of total work is left?
A7/15B11/18C7/18D8/15 - Question 2 - Select One or More
Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?
A3/5B2/3C7/12D5/12 - Question 3 - Select One
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days
A and B working together can complete the work in 12 days. A can complete the work in 20 days. If B does work for half day each day, then in what time can the work be completed.
View SolutionA man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View SolutionA can do a work in 15 days and B can do the same in 25 days. If they start the work together and B leaves 7 days before completion of the work then the work will be completed in how many days?
View SolutionA can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?
View Solution