Doubtnut Promotions Sticky

A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?

A

9

B

12

C

25

D

27

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work rates of A and B, then calculate how much work they complete together in 3 days, and finally convert that into a percentage of the total work.

Step 1: Determine the work rates of A and B
- A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 work per day

- B can complete the work in 25 days. Therefore, B's work rate is:
Work rate of B=125 work per day

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=Work rate of A+Work rate of B=120+125

- To add these fractions, we need a common denominator. The least common multiple of 20 and 25 is 100.
120=5100,125=4100
Combined work rate=5100+4100=9100 work per day

Step 3: Calculate the total work done in 3 days
- In 3 days, the amount of work completed by A and B together is:
Work completed in 3 days=Combined work rate×3=9100×3=27100

Step 4: Convert the work done into a percentage of the total work
- To find the percentage of the total work completed, we multiply the fraction of work completed by 100:
Percentage of work completed=27100×100=27%

Final Answer
Thus, the percentage of the total work completed by A and B together in 3 days is 27%.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Rahul can complete a work in 18 days and Sonu can complete the same work in 15 days. If both together work for 5 days, then what part of total work is left?

    A7/15
    B11/18
    C7/18
    D8/15
  • Question 2 - Select One or More

    Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?

    A3/5
    B2/3
    C7/12
    D5/12
  • Question 3 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days