A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it:
Find the number of days in which client wanted to complete his work.

A

15

B

10

C

8

D

can't be determined

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it: Find the number of days in which client wanted to complete his work. by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor undertook a project to complete it, in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it:
    How many men were working on the day the project was completed as per the date of client wanted to complete it?

    A5
    B10
    C20
    Dnone of these
  • The simple interest accrued on a sum of certain principal is 1200 in 4 year at the rate of 8% per annum. What would be the simple interest accured on thrice of that principal at the rate of 6% per annum in 3 year ?

    A2025
    B3025
    C2250
    D2150
  • A man working 6 hours a day takes 8 days to complete a project. How many hours a day must he work to complete. It in 3 days?

    A16
    B10
    C20
    D15