The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
8
7.5
8.5
912
The correct Answer is:A
To solve the problem, we need to find out how many days A, B, and C will take to complete the work when they work alternatively. Let's break it down step by step.
Step 1: Calculate the work efficiency of A, B, and C
- A can complete the work in 6 days, so A's work efficiency is:
Efficiency of A=16 (work per day)
- B can complete the work in 12 days, so B's work efficiency is:
Efficiency of B=112 (work per day)
- C can complete the work in 8 days, so C's work efficiency is:
Efficiency of C=18 (work per day)
Step 2: Calculate the total work done in 3 days
Since they work alternatively, the work done in 3 days (A works on Day 1, B on Day 2, and C on Day 3) is:
Total work in 3 days=Efficiency of A+Efficiency of B+Efficiency of C
Substituting the efficiencies:
=16+112+18
Step 3: Find the least common multiple (LCM) to add the fractions
The LCM of 6, 12, and 8 is 24. We convert each fraction:
- For A:
16=424
- For B:
112=224
- For C:
18=324
Now adding them together:
Total work in 3 days=424+224+324=924=38
Step 4: Calculate how many sets of 3 days are needed to complete the work
Since 38 of the work is done in 3 days, we can find out how many such sets are needed to complete 1 whole work:
Number of sets required=138=83
Step 5: Calculate the total number of days
Each set takes 3 days, so the total number of days required to complete the work is:
Total days=3×83=8 days
Final Answer
Thus, the total number of days needed to complete the whole work is 8 days.
---
- A can complete the work in 6 days, so A's work efficiency is:
Efficiency of A=16 (work per day)
- B can complete the work in 12 days, so B's work efficiency is:
Efficiency of B=112 (work per day)
- C can complete the work in 8 days, so C's work efficiency is:
Efficiency of C=18 (work per day)
Since they work alternatively, the work done in 3 days (A works on Day 1, B on Day 2, and C on Day 3) is:
Total work in 3 days=Efficiency of A+Efficiency of B+Efficiency of C
Substituting the efficiencies:
=16+112+18
The LCM of 6, 12, and 8 is 24. We convert each fraction:
- For A:
16=424
- For B:
112=224
- For C:
18=324
Total work in 3 days=424+224+324=924=38
Since 38 of the work is done in 3 days, we can find out how many such sets are needed to complete 1 whole work:
Number of sets required=138=83
Each set takes 3 days, so the total number of days required to complete the work is:
Total days=3×83=8 days
Thus, the total number of days needed to complete the whole work is 8 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?
View SolutionA and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View Solution
Knowledge Check
The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?
A8B7.5C8.5D912A, B and C can do piece of work in 18,24 and 36 days respectively . They work alternately , first day C, second day B and third day A, fourth day C and so on. How many days will be needed to complete the work like this way?
A18B20C24D30Alen and Border can do a work individually in 21 and 42 days respectively. In how many days they can complete the work, working alternatively?
A14B28C42D35
A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution