The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?

A

8

B

7.5

C

8.5

D

912

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to find out how many days A, B, and C will take to complete the work when they work alternatively. Let's break it down step by step.

Step 1: Calculate the work efficiency of A, B, and C
- A can complete the work in 6 days, so A's work efficiency is:
Efficiency of A=16 (work per day)
- B can complete the work in 12 days, so B's work efficiency is:
Efficiency of B=112 (work per day)
- C can complete the work in 8 days, so C's work efficiency is:
Efficiency of C=18 (work per day)

Step 2: Calculate the total work done in 3 days
Since they work alternatively, the work done in 3 days (A works on Day 1, B on Day 2, and C on Day 3) is:
Total work in 3 days=Efficiency of A+Efficiency of B+Efficiency of C
Substituting the efficiencies:
=16+112+18

Step 3: Find the least common multiple (LCM) to add the fractions
The LCM of 6, 12, and 8 is 24. We convert each fraction:
- For A:
16=424
- For B:
112=224
- For C:
18=324

Now adding them together:
Total work in 3 days=424+224+324=924=38

Step 4: Calculate how many sets of 3 days are needed to complete the work
Since 38 of the work is done in 3 days, we can find out how many such sets are needed to complete 1 whole work:
Number of sets required=138=83

Step 5: Calculate the total number of days
Each set takes 3 days, so the total number of days required to complete the work is:
Total days=3×83=8 days

Final Answer
Thus, the total number of days needed to complete the whole work is 8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?

    A8
    B7.5
    C8.5
    D912
  • A, B and C can do piece of work in 18,24 and 36 days respectively . They work alternately , first day C, second day B and third day A, fourth day C and so on. How many days will be needed to complete the work like this way?

    A18
    B20
    C24
    D30
  • Alen and Border can do a work individually in 21 and 42 days respectively. In how many days they can complete the work, working alternatively?

    A14
    B28
    C42
    D35