Anand can do a piece of work in 45 days, but Bahuguna can do the same work in 5 days less, than Anand, when working alone. Anand and Bahuguna both started the work together but Bahuguna left after some days and Anand finished the remaining work in 56 days with half of his efficiency but he did the work with Bahuguna with his complete efficiency. For how many days they had worked together?
6
8
9
12
The correct Answer is:B
To solve the problem, we need to determine how many days Anand and Bahuguna worked together before Bahuguna left. Let's break down the solution step by step.
Step 1: Determine the work rates of Anand and Bahuguna
- Anand can complete the work in 45 days.
- Bahuguna can complete the work in 40 days (5 days less than Anand).
The work done by each person in one day can be calculated as follows:
- Work rate of Anand = 145 (work per day)
- Work rate of Bahuguna = 140 (work per day)
Step 2: Calculate the combined work rate of Anand and Bahuguna
When Anand and Bahuguna work together, their combined work rate is:
Combined work rate=Work rate of Anand+Work rate of Bahuguna=145+140
To add these fractions, we need a common denominator. The least common multiple of 45 and 40 is 360.
145=8360,140=9360
Thus,
Combined work rate=8360+9360=17360
This means together they can complete 17360 of the work in one day.
Step 3: Determine the total work done after Bahuguna leaves
Let x be the number of days Anand and Bahuguna worked together. The amount of work they completed together in x days is:
Work done together=x×17360
After Bahuguna leaves, Anand finishes the remaining work in 56 days at half his efficiency. His work rate at half efficiency is:
Half efficiency of Anand=12×145=190
The amount of work Anand completes in 56 days at half efficiency is:
Work done by Anand alone=56×190=5690=2845
Step 4: Set up the equation for total work
The total work is equal to the work done together plus the work done by Anand alone:
1=x×17360+2845
Step 5: Solve for x
First, convert 2845 to a fraction with a denominator of 360:
2845=28×845×8=224360
Now substitute this into the equation:
1=x×17360+224360
Multiply through by 360 to eliminate the denominator:
360=17x+224
Now, isolate x:
17x=360−224
17x=136
x=13617=8
Conclusion
Anand and Bahuguna worked together for 8 days.
- Bahuguna can complete the work in 40 days (5 days less than Anand).
- Work rate of Bahuguna = 140 (work per day)
17x=136
x=13617=8
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)55videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round15videos
TIME AND WORK
- BOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)20videos
THEORY OF EQUATIONS
- BOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)10videos
TIME, SPEED AND DISTANCE
Similar Questions
A and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View Solution
Knowledge Check
- Question 1 - Select One
Anand can do a piece of work in 45 days, but Bahuguna can do the same work in 5 days less, than Anand, when working alone. Anand and Bahuguna both started the work together but Bahuguna left after some days and Anand finished the remaining work in 56 days with half of his efficiency but he did the work with Bahuguna with his complete efficiency. For how many days they had worked together?
A6B8C9D12 - Question 2 - Select One
A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :
A9B8C10D6 - Question 3 - Select One
A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?
A3B5C7D9
A can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionKiran alone can do a piece of work in 15 days and Aman can do the same in 10 days. If they start working together, in how many days can the work be completed?
View SolutionA can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
View Solution