Kavita, Babita and Samita started a work. 5 days later Samita left the work and Babita left the work after working 8 days. In how many more days Kavita would have completed the rest work if they take 20, 60 and 30 days individually to finish a work?
4
5
6
8
The correct Answer is:C
To solve the problem step by step, we will follow the outlined approach:
Step 1: Determine the work rates (efficiencies) of Kavita, Babita, and Samita.
- Kavita takes 20 days to complete the work, so her work rate is:
Efficiency of Kavita=120
- Babita takes 60 days to complete the work, so her work rate is:
Efficiency of Babita=160
- Samita takes 30 days to complete the work, so her work rate is:
Efficiency of Samita=130
Step 2: Calculate the total work done by each person during their respective working days.
- Samita works for 5 days:
Work done by Samita=5×130=530=16
- Babita works for 8 days:
Work done by Babita=8×160=860=215
Step 3: Calculate the total work done by Kavita, Babita, and Samita together.
- The total work done by Samita and Babita together in the first 8 days is:
Total work done=16+215
- To add these fractions, we need a common denominator. The LCM of 6 and 15 is 30.
- Convert 16 to 530
- Convert 215 to 430
So,
Total work done=530+430=930=310
Step 4: Calculate the remaining work.
- The total work is considered as 1 unit, so the remaining work after 8 days is:
Remaining work=1−310=710
Step 5: Determine how long it will take Kavita to complete the remaining work alone.
- Kavita's efficiency is 120, so the time t taken by Kavita to complete 710 of the work is given by:
Time=Remaining workEfficiency of Kavita=710120=710×20=14 days
Step 6: Determine how long it would take all three working together to complete the work.
- The combined efficiency of Kavita, Babita, and Samita is:
Combined efficiency=120+160+130
- The LCM of 20, 60, and 30 is 60.
- Convert 120 to 360
- Convert 160 to 160
- Convert 130 to 260
So,
Combined efficiency=360+160+260=660=110
- This means they can complete the work together in 10 days.
Step 7: Calculate the difference in time taken by Kavita and the combined group.
- Kavita takes 14 days, and the group takes 10 days, so the difference is:
Difference=14−10=4 days
Final Answer:
Kavita would take 4 more days to complete the rest of the work alone.
---
- Kavita takes 20 days to complete the work, so her work rate is:
Efficiency of Kavita=120
- Babita takes 60 days to complete the work, so her work rate is:
Efficiency of Babita=160
- Samita takes 30 days to complete the work, so her work rate is:
Efficiency of Samita=130
- Samita works for 5 days:
Work done by Samita=5×130=530=16
- Babita works for 8 days:
Work done by Babita=8×160=860=215
- The total work done by Samita and Babita together in the first 8 days is:
Total work done=16+215
- To add these fractions, we need a common denominator. The LCM of 6 and 15 is 30.
- Convert 16 to 530
- Convert 215 to 430
So,
Total work done=530+430=930=310
- The total work is considered as 1 unit, so the remaining work after 8 days is:
Remaining work=1−310=710
- Kavita's efficiency is 120, so the time t taken by Kavita to complete 710 of the work is given by:
Time=Remaining workEfficiency of Kavita=710120=710×20=14 days
- The combined efficiency of Kavita, Babita, and Samita is:
Combined efficiency=120+160+130
- The LCM of 20, 60, and 30 is 60.
- Convert 120 to 360
- Convert 160 to 160
- Convert 130 to 260
Combined efficiency=360+160+260=660=110
- This means they can complete the work together in 10 days.
- Kavita takes 14 days, and the group takes 10 days, so the difference is:
Difference=14−10=4 days
Kavita would take 4 more days to complete the rest of the work alone.
Topper's Solved these Questions
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - EXERCISE(LEVEL 2)
55 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- TIME AND WORKBOOK - ARIHANT SSCCHAPTER - TIME AND WORKEXERCISE - Final Round
15 Videos
- THEORY OF EQUATIONSBOOK - ARIHANT SSCCHAPTER - THEORY OF EQUATIONSEXERCISE - EXERCISE(LEVEL 2)
20 Videos
- TIME, SPEED AND DISTANCEBOOK - ARIHANT SSCCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - SPEED TEST (TSD)
10 Videos
Similar Questions
A and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View SolutionA can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View Solution
Knowledge Check
A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
A203 daysB253 daysC6 daysD5 daysA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C40D50
A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?
View Solution13.A and B together can do a work in 25days. They work to together for 15days and then B leaves.A finishes the rest of the work in 20 days.How many days would each take to complete the work seperately?
View SolutionVinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
View SolutionVinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
View SolutionA can finish work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work?
A 20 दिनों में कार्य समाप्त कर सकता है तथा B इसी कार्य को 25 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन B ने 5 दिनों के बाद कार्य छोड़ दिया | शेष कार्य पूरा करने में A को कितने अतिरिक्त दिन लगेंगे ?
View Solution