Kareena can do a piece of work in 9 days and Karishma can do the same work in 18 days. They started the work. After 3 days Shahid joined them, who can complete alone the same whole work in 3 days. What is the total number of days in which they had completed the work?

A

12

B

8

C

4

D

6

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the work efficiency of each person.
- Kareena's efficiency: She can complete the work in 9 days. Therefore, her efficiency is:
Efficiency of Kareena=1 work9 days=19

- Karishma's efficiency: She can complete the work in 18 days. Therefore, her efficiency is:
Efficiency of Karishma=1 work18 days=118

- Shahid's efficiency: He can complete the work in 3 days. Therefore, his efficiency is:
Efficiency of Shahid=1 work3 days=13

Step 2: Calculate the total work done by Kareena and Karishma in the first 3 days.
- Together, their combined efficiency for one day is:
Combined efficiency=19+118
To add these fractions, we find a common denominator (which is 18):
19=218
So,
Combined efficiency=218+118=318=16

- In 3 days, the work done is:
Work done in 3 days=3×16=36=12

Step 3: Calculate the remaining work.
- After 3 days, half of the work is completed. Therefore, the remaining work is:
Remaining work=112=12

Step 4: Calculate the combined efficiency when Shahid joins.
- Now, all three (Kareena, Karishma, and Shahid) are working together. Their combined efficiency is:
Total efficiency=19+118+13
Again, finding a common denominator (which is 18):
19=218,13=618
So,
Total efficiency=218+118+618=918=12

Step 5: Calculate the time taken to complete the remaining work.
- The time taken to complete the remaining work of 12 at a rate of 12 work per day is:
Time taken=Remaining workTotal efficiency=1212=1 day

Step 6: Calculate the total time taken to complete the work.
- The total time taken is the sum of the time worked by Kareena and Karishma alone and the time worked together with Shahid:
Total time=3 days+1 day=4 days

Final Answer:
The total number of days in which they completed the work is 4 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Kareena can do a piece of work in 9 days and Karishma can do the same work in 18 days. They started the work. After 3 days Shahid joined them, who can complete alone the same whole work in 3 days. What is the total number of days in which they had completed the work?

    A12
    B8
    C4
    D6
  • Raja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :

    A7
    B8.5
    C5
    D1015
  • A can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together?

    A2 days
    B3 days
    C4 days
    D5 days