A plumber works twice as fast as his apprentice. After the plumber has worked alone for 3 hours, his apprentice joins him and working together they complete the job 4 hours later. How many hours would it have taken the plumber to do the entire job by himself?

A

9

B

12

C

14

D

18

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will define the work rates of the plumber and his apprentice, calculate the work done in different time intervals, and finally determine how long it would take the plumber to complete the job alone.

Step 1: Define Work Rates
Let the work rate of the apprentice be 1 unit per hour. Since the plumber works twice as fast as his apprentice, his work rate will be:
Work rate of plumber=2×Work rate of apprentice=2×1=2 units per hour

Hint: Define the work rates based on the relationship given in the problem.

Step 2: Calculate Work Done by the Plumber Alone
The plumber works alone for 3 hours. The work done by the plumber in this time is:
Work done by plumber in 3 hours=Work rate of plumber×Time=2 units/hour×3 hours=6 units

Hint: Use the formula for work done: Work = Rate × Time.

Step 3: Calculate Work Done Together
After 3 hours, the apprentice joins the plumber, and they work together for 4 hours. The combined work rate when they work together is:
Combined work rate=Work rate of plumber+Work rate of apprentice=2 units/hour+1 unit/hour=3 units/hour
The work done together in 4 hours is:
Work done together in 4 hours=Combined work rate×Time=3 units/hour×4 hours=12 units

Hint: Add the work rates to find the combined rate when working together.

Step 4: Calculate Total Work Done
Now, we can find the total work done:
Total work=Work done by plumber alone+Work done together=6 units+12 units=18 units

Hint: Sum the work done in each phase to find the total work.

Step 5: Calculate Time for Plumber to Complete the Job Alone
To find out how long it would take the plumber to complete the entire job by himself, we use the formula:
Time taken by plumber=Total workWork rate of plumber=18 units2 units/hour=9 hours

Hint: Use the formula for time: Time = Work / Rate.

Final Answer
The plumber would take 9 hours to complete the entire job by himself.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If x people working together at the same rate can complete a job in h hours, what part of the same job can one person working alone complete in k hours?

    Akxh
    Bhxk
    Ckx+h
    Dkhx
  • Ana and Amy started a landscaping job together. When Ana stopped, she had completed 25 of the job. When Amy stopped, she had completed 13 of the job. Then Ruben complete the rest of the job in 2 hours. Assume that Ana, Amy and Ruben all worked at the same rate. Which of the following values is closest to the number of hours it would have taken 1 of them to complete the entire job alone?

    A0.37
    B1.27
    C2.73
    D7.50
  • If took 12 men 5 hours to build an airstrip. Working at the same rate, how many additional men could have been hired in order for the job to have taken 1 hour less?

    ATwo
    BThree
    CFour
    DSix