40 men can complete a piece of work in 18 days. Eight days after they started working together 10 more men joined them. How many days will they now take to complete the remaining work ? a 6 days b 8 days c 10 days d 12 days
Correct option b 8 daysExplanation: Let ‘D’ days required to complete the job
Related Solutions
12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution12 men can do a piece of work in 90 days. After 30 days from the start of the work 2 men left the work and 8 men joined. In how many days will it take to complete the remaining work?
View Solution15 men can complete a work in 24 days and 12 children in 60 days. 10 men started the work and after 12 days 12 children joined the work. In how many days will the remaining work be finished?
View Solution18 men can do a piece of work in 9 days. After working for 5 days 6 more men join them. In how many days will they take to complete the remaining work?
View Solution45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View Solution18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionIf 30 men working 8 hours a day can complete a piece of work in 10 days, then how many hours per day must 40 men work so that they can complete it in 6 days?
View Solution8 men can complete a work in 40 days. If 2 more men join them, how many days will it take to complete the same work?
View SolutionA' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
View Solution‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
View SolutionA piec of work can be done by 12 men in 24 days. They started the work and after 4 days then 6 more men joined them. How many days will they all take to complete the remaining work ?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View Solution12 men can do a piece of work in 9 days. After working for 6 days 6 more men are engaged in the work. In how many days will it take to complete the remaining work?
View Solution