Question

A company employed 200 workers to complete a certain work in 150 days. If only 1/4th of the work had 150 days. If only been done in 50 days then in order to complete the whole work in time the number of additional workers to be employed were: a 100 b 600 c 300 d 200

Text Solution
Verified by Experts

Correct option a 100 Explanation: M2= 300 So additional men = 300 – 200 =100


Related Solutions