A company employed 200 workers to complete a certain work in 150 days. If only 1/4th of the work had 150 days. If only been done in 50 days then in order to complete the whole work in time the number of additional workers to be employed were: a 100 b 600 c 300 d 200
Correct option a 100 Explanation: M2= 300 So additional men = 300 – 200 =100
Related Solutions
A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
View Solutionएक कंपनी ने 150 दिन में किसी काम को पूरा करने के लिए 200 कामगारों को नियक्त किया यदि 50 दिन में केवल एक चौथाई काम पूरा हुआ हो तो पुरे काम को समय पर पूरा करने में कितने अतिरिक्त कामगार लगाने पड़ेगे ?
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: (A) 50 (B) 75 (C) 100 (D) 150
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionSolve the following :
420 workers take 15 days to complete a piece of work. How many more workers should be employed, if the same work is to be completed in 12 days? How many days will it take to complete the same work, if 300 workers were employed ?
View Solutionएक व्यक्ति किसी काम को 150 दिनों में पूरा करने का टेका लेता है और इसके लिए वह 200 लोगो को काम पर लगता है 50 दिनों के बाद वह पता है कि केवल एक चौथाई काम हो पाया है , तो समय पर काम पूरा करने के लिए कितने अतिरिक्त लोगो को काम पर लगता होगा ?
View Solution20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?
View Solution20 workers working for 5 hours a day complete a work in 10 days . If 25 workers are employed to work 10 hours a day, what is the time required to complete the work ?
View Solutionਕਿਸੇ ਕੰਮ ਨੂੰ ਕੁਝ ਦਿਨਾਂ ਵਿੱਚ ਪੂਰਾ ਕਰਨ ਲਈ 150 ਮਜ਼ਦੂਰ ਲਗਾਏ ਗਏ। ਦੂਜੇ ਦਿਨ 4 ਮਜ਼ਦੂਰਾਂ ਨੇ ਕੰਮ ਛੱਡ ਦਿੱਤਾ, ਤੀਜੇ ਦਿਨ 4 ਹੋਰ ਕਰਮਚਾਰੀਆਂ ਨੇ ਕੰਮ ਛੱਡ ਦਿੱਤਾ ਅਤੇ ਇਸ ਤਰ੍ਹਾਂ ਹੋਰਾਂ ਨੇ।ਹੁਣ ਕੰਮ ਪੂਰਾ ਕਰਨ ਵਿੱਚ 8 ਦਿਨ ਵੱਧ ਲੱਗਦੇ ਹਨ ਤਾਂ ਦਿਨਾਂ ਦੀ ਸੰਖਿਆ ਦੱਸੋ ਜਿਸ ਵਿੱਚ ਕੰਮ ਪੂਰਾ ਕੀਤਾ ਗਿਆ।
View SolutionA contractor undertook a work to complete in 60 days. But just after 20 days he observed that only of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
View Solutionकामगार दिन में घण्टे काम कर एक काम को दिनों में पूरा करते है। यदि कामगारों को दिन में घण्टे काम करने के लिए लगाया जाता है तो काम के पूरा होने का आवश्यक समय क्या है ?
View SolutionA contractor employed 100 laborers to complete a work in 96 days. But only 1/7 of the work was done in 1/6 of the stipulated time. The number of additional laborers required to complete the work in time is
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View SolutionSanjay took a contract to finish a work in 32 days 8 workers were absent from the beginning and rest of the workers completed the whole work in 36 days. How many laborers were initially employed?
View SolutionIf they are in G.P.Write next one terms.
a,2a, 3a, 4a,......
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'x' then
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View Solution