Solve the following :
420 workers take 15 days to complete a piece of work. How many more workers should be employed, if the same work is to be completed in 12 days? How many days will it take to complete the same work, if 300 workers were employed ?Solution in Marathi
105 more workers, 21 days.
Topper's Solved these Questions
Similar Questions
Find the volume of a box if its length, breadth and height are 20 cm,10.5 cm and 8 cm respectively.
View Solutionएक कंपनी ने 150 दिन में किसी काम को पूरा करने के लिए 200 कामगारों को नियक्त किया यदि 50 दिन में केवल एक चौथाई काम पूरा हुआ हो तो पुरे काम को समय पर पूरा करने में कितने अतिरिक्त कामगार लगाने पड़ेगे ?
View Solution27. 15 people completed a work in 7 days 10 How many days should people take to complete this work?
View Solution56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?
View Solution20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work?
View Solution30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.
View Solutionਕਿਸੇ ਕੰਮ ਨੂੰ ਕੁਝ ਦਿਨਾਂ ਵਿੱਚ ਪੂਰਾ ਕਰਨ ਲਈ 150 ਮਜ਼ਦੂਰ ਲਗਾਏ ਗਏ। ਦੂਜੇ ਦਿਨ 4 ਮਜ਼ਦੂਰਾਂ ਨੇ ਕੰਮ ਛੱਡ ਦਿੱਤਾ, ਤੀਜੇ ਦਿਨ 4 ਹੋਰ ਕਰਮਚਾਰੀਆਂ ਨੇ ਕੰਮ ਛੱਡ ਦਿੱਤਾ ਅਤੇ ਇਸ ਤਰ੍ਹਾਂ ਹੋਰਾਂ ਨੇ।ਹੁਣ ਕੰਮ ਪੂਰਾ ਕਰਨ ਵਿੱਚ 8 ਦਿਨ ਵੱਧ ਲੱਗਦੇ ਹਨ ਤਾਂ ਦਿਨਾਂ ਦੀ ਸੰਖਿਆ ਦੱਸੋ ਜਿਸ ਵਿੱਚ ਕੰਮ ਪੂਰਾ ਕੀਤਾ ਗਿਆ।
View Solution10 मजदूर किसी काम को 2 दिन में करते हैं उसी काम को 2 मजदूर कितने दिनों में करेंगे?
View Solution45 मजदूर एक काम को 27 दिनों में पूरा करते हैं तो कितने मजदूर उसी काम को 15 दिनों में पूरा करेंगे?
View SolutionA' completes a work in 12 days 'B' completes the same work in 15 days .A started working alone and after 3 days B joined him .How many days will they now take together to complete the remaining work ?
View SolutionSanjay took a contract to finish a work in 32 days 8 workers were absent from the beginning and rest of the workers completed the whole work in 36 days. How many laborers were initially employed?
View SolutionA work can be completed by 3 men in one day. same work by 8 women 3/4 is completed in a day or the same work can be completed in half a day by 18 children working. If 3 women and 3 children are employed for a day, then for how many days should a man be employed to complete the work?
View SolutionA company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
View Solution‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?
View SolutionHow many workers are required for completing the construction work in the 10 days ?
(i) 20% of the work can be completed by 8 workers in 8 days.
(ii) 20 workers can complete the work in 16 days.
(iii) One - eighth of the work can ve completed by 8 workers in 5 days.
View Solution