A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: a 75 b 100 c 125 d 50
Correct option b 100 Explanation:Let ’n’ number of men are required.
Related Solutions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: (A) 50 (B) 75 (C) 100 (D) 150
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View SolutionA company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
(A) 50 (B) 75 (C) 100 (D) 150
View Solution120 men working 10 hours a day can finish a piece of work in 85 days. After 10 days all the men went on strike and the work was stopped for 25 days. In order to finish the work on time, additional men should be employed so that they can finish the work on time by working 8 hours a day?
View SolutionA contractor took a contract to complete a work in 150 days. He employed 20 men, 30 women and 75 children for him. But after 60 days he found that only a quarter of the work was finished. Seeing this, he fired all the women and 50 children and employed some more men. On doing so the work got finished 5 days before the scheduled time. Assuming that 3 men do as much work as 5 women and 2 women do as much work as 3 children, then how many additional men did the contractor employ?
View SolutionA contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View SolutionA contractor employs 36 men on a job and they do 1/2 of the work in 16 days. He employs 12 additional men to complete the remainder of the work. In how many days will the remaining work be finished?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View Solution36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?
View SolutionA contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done part of the work, the number of men he can withdraw so that the work may still be finished in time is :
View Solution60 men can finish a work in 50 days. If 20 men join the work every 10 days, then in how many days will the work be finished?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
View SolutionA certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View Solution