A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
(A) 50 (B) 75 (C) 100 (D) 150
100
125
50
75
The correct Answer is:A
200×50=10000
10000 व्यक्तियों के द्वारा 14 कार्य होता है।
∴ पूरे कार्य के लिए 40000 व्यक्तियों की आवश्यकता है। ∴ अतिरिक्त मजदूरों की संख्या = =40000−200×150100
=40000−30000100=10000100=100
Similar Questions
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View Solution15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
View Solution
Knowledge Check
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is:
(A) 50 (B) 75 (C) 100 (D) 150A100B125C50D75A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 35 part of the work, the number of men he can withdraw so that the work may still be finished in time is :
A45B40C35D30A contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?
A30B20C15D10
16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 23 of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertakes to make a mall in 60 days and he
employs 30 men. After 30 days it is found that only one-
third of the work is completed. How many extre men should
he employ so that the work is completed on time?
View SolutionA contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
View Solution9 men finish one-third work in 10 days. The number of additional men required for finishing the remaining work in 2 more days will be
View Solution